Self Studies

Numerical Applications Test 48

Result Self Studies

Numerical Applications Test 48
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    1 / -0
    The average of statistical data is called :
    Solution
    The average of statistical data is called $$Mean$$ or $$Arithmatic\ mean$$

    Hence, $$Op-A$$ is correct.
  • Question 2
    1 / -0
    Two men and $$5$$  boys together can finish a piece of work in  $$4$$ days, while $$3 $$ men and $$ 6$$  boys can finish in $$3$$  days. Find the time taken :
    (i) by one man alone to finish the work
    (ii) by one boy alone to finish the work.
    Solution
    Let the amount of work done by a Man alone in a day be $$ M $$ and by a Boy alone be $$ B $$

    Given, $$2$$ men and $$5$$ boys together can finish a piece of work in $$ 4 $$ days

    Amount of work they can do in one day $$2M + 5B $$$$ = \dfrac {1}{4} $$ -- (1)

    Similarly, $$ 3M + 6 B = \dfrac {1}{3} $$ --- (2)

    Solving equations $$ (1) $$ and $$ (2) $$, we get $$ B = \dfrac {1}{36} $$

    Substituting $$ B $$ in equation $$ 2 $$, we get $$ M = \dfrac {1}{18} $$

    Hence, one man alone will take $$ 18 $$ days to do the work and one boy will take $$ 36 $$ days.

  • Question 3
    1 / -0
    A contractor undertakes to dig a canal, $$6$$ kilometers long in $$35$$ days and employed $$90$$ men. He finds that after $$20$$ days only $$2$$ km of canal have been completed . How many more men must be employed to finish the work in time?
    Solution
    Total time given $$=35$$ days.

    To dig a canal of $$2$$ km in $$20$$ days, $$90$$ men were required.

    So, to dig a canal of $$1$$ km in $$1$$ day, $$\dfrac{90\times20}{2}$$ men will be required.

    So, to dig a canal of $$4$$ km in $$15$$ days $$\dfrac{900\times4}{15}$$ $$=240$$ men will be required.

    As $$90$$ men were already employed, so $$150$$ more men are required.
  • Question 4
    1 / -0
    Pooja and Ritu can do a piece of work in $$17\displaystyle \frac{1}{7}$$ days. If one day work of Pooja be three fourth of one day work of Ritu; find in how many days each alone will do the work.
    Solution
    Let Pooja's one day work be $$x$$
    And Ritu's one day work be $$y$$
    Accprding to first condition,
    Pooja and Ritu can do work in $$17 \dfrac{1}{7}$$ days i.e $$\dfrac{120}{7}$$ days
    $$\therefore x + y = \dfrac {1}{\dfrac{120}{7}}$$ 
    $$\therefore x + y = \dfrac{7}{120}$$  .........Equation $$1$$
    According to second condition,
    $$x = \dfrac{3}{4} y$$
    $$\therefore 4x - 3y = 0$$   .......... Equation $$2$$
    Multiplying eqution $$1$$ by $$3$$ and solving equation $$1$$ and $$2$$ simultaneosly, we get
    $$3x + 3y = \dfrac{7}{40}$$
    $$4x - 3y = 0$$
    $$\therefore 7x = \dfrac{7}{40}$$
    $$\therefore x = \dfrac{1}{40}$$
    Putting the value of $$x$$ in equation $$1$$ , we get
    $$\dfrac{1}{40} + y = \dfrac{7}{120}$$
    $$\therefore y = \dfrac{4}{120} = \dfrac{1}{30}$$
    $$\therefore$$ Pooja's one day work is $$x = \dfrac{1}{40}$$ 
    i.e. her whole work will be completed in $$40$$ days
    Similarly Pooja's work will be completed in $$30$$ days
    Answer : Pooja can do the work alone in $$40$$ days and Ritu in $$30$$ days
  • Question 5
    1 / -0
    A cabinet of ministers consists of 11 ministers, one minister being the chief minister. A meeting is to be held in a room having a round table and 11 chairsround it, one of them being meant for the chairman. The number of ways in which the ministers can take their chairs, the chief minister occupying the chairman's place, is
    Solution
    These are circular permutations
    so,
    $$=(n-1)!$$ = $$10!$$
  • Question 6
    1 / -0
    $$16$$ men can complete a work in $$12$$ days, $$24$$ children can complete the same work in $$18$$ days, $$12$$ men and $$8$$ children started working and after $$8$$ days, $$3$$ more children joined them. How many days will they now take to complete the remaining work ?
    Solution
    One day work of 16 men is $$\dfrac { 1 }{ 12 } $$.

    One day work of 24 children is $$\dfrac { 1 }{ 18 } $$.

    One men's one day work is $$\dfrac { 1 }{ 12\times 16 } $$.

    One child's one day work is $$\dfrac { 1 }{ 24\times 18 } $$.

    One day work of 12 men and 8 children is $$\dfrac { 12 }{ 12\times 16 } +\dfrac { 8 }{ 24\times 18 } $$.

    One day work = $$\dfrac { 35 }{ 54\times 8 } $$.

    Work done in 8 days = $$8\times \dfrac { 35 }{ 54\times 8 } =\dfrac { 35 }{ 54 } $$.

    Remaining work = $$1-\dfrac { 35 }{ 54 } =\dfrac { 19 }{ 54 } $$.

    The remaining work is 12$$\times$$ one men's one day work + 11$$\times$$ one child's one day work.

    Hence, $$12\times \dfrac { 1 }{ 12\times 16 } +11\times 24\times 18$$

    One day work multiplied by number of days to complete remaining work =  remaining work

    Therefore, the work is done in 4 days.

    $$\left( \dfrac { 1 }{ 16 } +\dfrac { 11 }{ 24 } \times 18 \right) x=\dfrac { 19 }{ 54 } $$

    $$\Rightarrow $$$$x=4$$

    Thus they take 4 days to complete the remaining work.

    Hence option B is correct.
  • Question 7
    1 / -0
    A particular work can be completed by $$6$$ men and $$6$$ women in $$24$$ days, whereas the same work can be completed by $$8$$ men and $$12$$ women in $$15$$ days. Find the time taken by $$4$$ men and $$6$$ women to complete the same work .
    Solution
    From the question, we have
    ($$6$$ men and $$6$$ women) $$1$$ day work $$=\dfrac{1}{24}$$

    ($$12$$ men and $$12$$ women)$$1$$ day work$$=\dfrac{1}{12}$$   ...     (1)

    ($$8$$ men and $$12$$ women)$$1$$ day work$$=\dfrac{1}{15}$$     ...    (2)
    Subtracting (1) and (2), we get
    $$4$$ men work $$=\dfrac{1}{12}$$  $$-\dfrac{1}{15}$$ $$=\dfrac{1}{60}$$  

    $$2$$ men work $$=\dfrac{1}{120}$$  

    $$4$$ men and $$6$$ women work $$=1$$ day work of $$6$$ men and $$6$$ women  $$-1$$ day work of $$2$$ men.
    $$=\dfrac{1}{24}$$ $$-\dfrac{1}{120}$$ $$=\dfrac{4}{120}$$  $$=\dfrac{1}{30}$$  

    The time taken by $$4$$ men and $$6$$ women to complete the same work $$= 30$$ days.

    Hence, option B.
  • Question 8
    1 / -0
    $$A$$ and $$B$$ can do a piece of work in $$5$$ days, $$B$$ and $$C$$ can do it in $$7$$ days. $$A$$ and $$C$$ can do it in $$4$$ days. Who among these will take the least time if put to do it alone ?
    Solution
    $$Let \, \,the \, \,work \, \,be \, \,W.$$
    $$A \, \, and\, \, B\, \, can\, \, do\, \, a \, \, piece \, \,of\, \,  work\, \, in \, \, 5 \, \,days$$$$\therefore \, \,5A+5B=W \, \,..........(1)$$

    $$B \, \, and \, \, C \, \, can \, \,do \, \, it \, \, in \, \,7 \, \, days$$$$\therefore, \, \,7B+7C=W \, \,......(2)$$

    $$A \, \, and \, \, C \, \, can \, \,do \, \, it \, \, in \, \,4 \, \, days$$$$\therefore, \, \,4A+4C=W \, \,.......(3)$$

    $$Solving \, \, (1) \, \,(2) \, \,and \, \,(3) \, \,We \, \,get,$$

    $$Speed \, \, of \, \, A=\dfrac{43}{280} \, \, work/day$$

    $$Speed \, \, of \, \, B=\dfrac{13}{280} \, \, work/day$$

    $$Speed \, \, of \, \, C=\dfrac{27}{280} \, \, work/day$$

    $$Since \, \,speed \, \,of \, \,A \, \,is \, \,maximum \, \,among \, \,all \, \,three, \, $$
    $$Hence \, \,A \, \, will \, \,take \, \,least \, \,time \, \,to \, \,complete \, \,the \, \,work.$$
  • Question 9
    1 / -0
    A and B can do a job in $$12$$ days, B and C can do it in $$16$$ days. After A has worked for $$5$$ days and B has worked for $$7$$ days, C can finish the rest in $$13$$ days. In how many days, can C do the work alone?
    Solution
    $$A$$ and $$B$$ can do a job in $$12$$ days.
    $$B$$ and $$C$$ can do a job in $$16$$ days.
    $$A$$ worked for $$5$$ days and $$B$$ worked for $$7$$ days.
    Part of work done by $$A$$ and $$B$$ in $$5$$ days=$$\dfrac{5}{12}$$
    $$\therefore$$ Part of work left after $$A$$ left=$$1-\dfrac{5}{12}=\dfrac{12-5}{12}=\dfrac{7}{12}$$
    After $$A$$ left work $$B$$ worked for $$2$$ more days.
    Part of work done by $$B$$ and $$C$$ in $$2$$ days=$$\dfrac{2}{16}=\dfrac{1}{8}$$
    $$\therefore$$ part of work left after $$B$$ left=$$\dfrac{ 7 }{ 12 } -\dfrac{ 1 }{ 8 } =\dfrac{ 14-3 }{ 24 } =\dfrac{ 11 }{ 24 } $$
    Now $$\dfrac{ 11 }{ 24 }$$ part o work $$C$$ has to complete in $$11$$ days
    Since $$C$$ already had worked for $$2$$ dayswith $$B$$
    (part)complete work is done by $$C$$ in $$\dfrac { 11  }{ \dfrac { 11 }{ 24 }  } $$
    =$$24$$days.
  • Question 10
    1 / -0
    $$3$$ men and $$4$$ boys can do a piece of work in $$14$$ days, while $$4$$ men and $$6$$ boys do the same work in $$10$$ days. How long would it take one man to finish the same work ?
    Solution
    Let one man's one day's work be $$x$$
    Let one boy's one day's work be $$y$$
    According to first condition,
    $$3x+4y = \dfrac{1}{14}$$     .......Equation $$1$$
    According to second condition,
    $$4x+6Y = \dfrac{1}{10}$$     .......Equation $$2$$
    Multiplying Equation $$1$$ by $$4$$ and Equation $$2$$ by $$3$$,
    $$12x + 16y = \dfrac{4}{14}$$     .....Equation $$3$$
    $$12x + 18y = \dfrac{3}{10}$$     .....Equation $$4$$
    Now solving Equation $$3$$ and $$4$$ simultaneously by substracting Equation $$3$$ by Equation $$4$$,
     we get,
    $$\therefore -2y = \dfrac{4}{14} -\dfrac{3}{10}$$

    $$\therefore -2y = \dfrac{40-42}{140}$$

    $$\therefore y = \dfrac{1}{140}$$
    Putting the value of y in equation $$1$$, we get,
    $$3x + \dfrac{4}{140} = \dfrac{1}{14}$$

    $$\therefore x = \dfrac{1}{70}$$

    Hence one man's one day  work is $$\dfrac{1}{70}$$

    $$\therefore$$ one man completes the whole work in $$70$$ days.
Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now