Self Studies

Power Systems Test 2

Result Self Studies

Power Systems Test 2
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    1 / -0
    In pumped storage scheme, the generator is also used as
    Solution

    In pumped storage plant, synchronous generator is used as synchronous motor to pump the water back to the reservoir during off-peak period as pumped storage plant is mainly used for peak loads.

    During peak period, the generator may be used as synchronous condenser for VAR compensation to maintain the voltage profile of the system
  • Question 2
    1 / -0

    Among the following which is/are the baseload power station/plant?

    1) Hydroelectric

    2) Biogas

    3) Diesel

    4) Pumped storage
    Solution

    Baseload power station: Baseload is the minimum level of electricity demand required over a period of 24 hours. It is needed to provide power to components that keep running at all times (also referred to as continuous load). Plants that are running continuously over extended periods of time are said to be baseload power plants.

    Example:

    • Nuclear power plant
    • Coal or thermal power plant
    • Hydroelectric plant
    • Geothermal plant
    • Biogas plant
    • Biomass plant
    • Solar thermal with storage
    • Ocean thermal energy conversion

     

    Peak load power station: Peak load is the time of high demand. These peaking demands are often for only shorter durations. To cater to the demand peaks, peak load power plants are used. They are started up whenever there is a spike in demand and stopped when the demand recedes.

    Example:

    • Gas plant
    • Solar power plants
    • Wind turbines
    • Pumped storage plants
    • Diesel generators
    So, the solar power plant is different from other power plants.
  • Question 3
    1 / -0
    In a Steam power plant, _________ heats the feed water on its way to the boiler by deriving heat from the flue gases.
    Solution

    Superheaters: It is used to dry the wet steam and raise the temperature of the steam above its saturation temperature. It is generally placed in the path of the furnace gases so as to utilize the heat from the hot flue gases.

    Economizer: It is also known as a feedwater heater. It is a device in which the waste heat of the flue gases is utilized for heating the feed water.

    Air Preheater: It is used to increase the temperature of the air before it enters the furnace. It is generally placed after the economizer; so that the flue gases pass through the economizer and then to the air preheater.

  • Question 4
    1 / -0
    A steam power station spends Rs. 30 Lakhs per annum for coal used in the station. The coal has a calorific value of 5000 kcal/kg and costs Rs. 300 per ton. If the station has thermal efficiency of 33% and electrical efficiency of 90%, the average load on the station is
    Solution

    Overall efficiency of the station = 0.33 × 0.9 = 0.297

    Coad used per annum \(= \frac{{30\; \times \;{{10}^5}}}{{300}} = {10^4}\;tons = {10^7}kg\)

    Heat of combustion = Coal used/annum × calorific value

    = 107 × 5000 = 5 × 1010 kcal

    Heat output = overall efficiency × heat of combustion

    = 0.297 × 5 × 1010 = 1485 × 107 kcal

    Units generated/annum \(\frac{{1485\; \times \;{{10}^7}}}{{860}} = 17.26 \times {10^6}kWh\)

    Average load on station = (units generated per annum)/ hours in a year

    \(= \frac{{17.26\; \times \;{{10}^6}}}{{8760}} = 1971.1\;kW\)

  • Question 5
    1 / -0

    A run of river hydro plant with pondage has the following data:

    Installed capacity = 10 MW

    Water head = 20 m

    Overall efficiency = 80%

    Load factor = 40%

    If an a particular day, the river flow is 20 m3/sec, the load factor of the plant is _____ (in %)
    Solution

    Weight of water available/sec W = Q × 9.81 × 1000

    = 9810 Q N

    Average power produced = W × H × η

    = 9810 × 20 × 0.8 × Q W

    = 156.96 Q kW

    Power developed in a day = 156.96 × 20 = 3139.2 kW

    Units generated in a day = 3139.2 × 24 = 75,341 kWh

    Load factor \(= \frac{{75341\; \times\; {{10}^3}}}{{10\; \times \;{{10}^6} \times 24}} \times 100 = 31.4\% \)

  • Question 6
    1 / -0

    A generating station has a maximum demand of 25 MW, a load factor of 60%, a plant capacity factor of 50% and a plant use factor of 72%.

    The maximum energy that could be produced daily if the plant while running as per schedule, were full loaded is ______
    Solution

    Load factor = (Average demand)/maximum demand

    Average demand = 25 × 0.6 = 15 MW

    Daily energy produced = Average demand × 24

    = 15 × 24 = 360 MWh

    Maximum energy that could be produced

    = (Actual energy produced in a day)/(Plant use factor)

    \(= \frac{{360}}{{0.72}} = 500\;MWh/day\)
  • Question 7
    1 / -0
    A power station has a maximum demand of 15 MW. The annual load factor is 50% and plant capacity factor is 40%. The reserve capacity of the plant is ______ (in kW)
    Solution

    Energy generated/annum = Maximum demand × load factor × hours in a year

    = 15000 × 0.5 × 8760 = 65.7 × 106 kWh

    Plant capacity factor = (units generated/annum)/(Plant capacity × hours in a year)

    Plant capacity \(= \frac{{65.7\; \times \;{{10}^6}}}{{0.4\; \times \;8760}} = 18,750\;kW\)

    Reserve capacity = plant capacity – maximum demand

    = 18750 – 15000 = 3750 kW

  • Question 8
    1 / -0

    Which of the following are the advantages of interconnected operation of power system?

    1. Less reserve capacity requirement

    2. More reliability

    3. High power factor

    4. Reduction in short circuit level.

    select the correct answer using the codes given below
    Solution
    The advantages of interconnected operation of power systems are less reserve capacity requirement and more reliability.
  • Question 9
    1 / -0

    A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 10MW hr. Calculate load factor.

    Solution

    The load factor percentage is derived by dividing the total kilowatt-hours (kWh) consumed in a designated period by the product of the maximum demand in kilowatts (kW) and the number of hours in the period

    Maximum demand = 80 MW

    Connected load = 150 MW

    Units generated in one year = 400 × 103 MW hr

    Total number of hours in a year = 8760

    Average load = 400 × 103/8760 = 45.662 MW

    \(Load\;Factor = \frac{{Average\;load}}{{Maximum\;demand}} = \frac{{45.662}}{{80}} = 0.57\)

Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now