Self Studies

Industrial Engineering Test 4

Result Self Studies

Industrial Engineering Test 4
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    1 / -0

    A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?

    Solution

    Concept:

    The PERT (Project Evaluation and Review Technique) technique is used, when activity time estimates are stochastic in nature. For each activity, three values of time (optimistic, most likely, pessimistic) are estimated.

    • Optimistic time (to) estimate is the shortest possible time required for the completion of the activity
    • Most likely time (tm) estimate is the time required for the completion of activity under normal circumstances
    • Pessimistic time (tp) estimate is the longest possible time required for the completion of the activity


    In PERT expected time of an activity is determined by using the below-given formula:

    \({t_e} = \frac{{\left( {{t_o} + 4{t_m} + {t_p}} \right)}}{6}\)

    Variance, σ2 = \({\left[ {\frac{{{t_P} - {t_0}}}{6}} \right]^2}\)

    Calculation:

    Given, to = 3 days, tm = 10 days and tp = 8 days

    \({t_e} = \frac{{{t_o} + 4{t_m} + {t_p}}}{6} = \frac{{3 + 4\left( 10 \right) + 8}}{6} = \frac{{51}}{6} = 8.5 \ days\)

  • Question 2
    1 / -0
    A repair shop is manned by a single worker. Customers arrive at the rate of 30 per hour. Time required to provide service is exponentially distributed with mean of 100 seconds. The mean waiting time of a customer; needing repair facility in the queue is _______ minute
    Solution

    Concept:

    Mean waiting time of customer in queue,

    \({W_q} = \frac{\lambda }{{\mu \left( {\mu - \lambda } \right)}}\)

    Calculation:

    λ = 30 per hour

    \(\mu = \frac{{60\; \times \;60}}{{100}} = 36\;{\rm{per\;hour}}\)

    \(\therefore {W_q} = \frac{{30}}{{36\left( {36 - 30} \right)}}\)

    Wq = 0.138 hour

    ∴ Wq = 8.33 minute

  • Question 3
    1 / -0
    In a shop, customers arrive at rate of 20 per hour and are getting served at rate of 30 per hour. The waiting time of customer in the queue is
    Solution

    Explanation:

    Given:

    λ = 20/hour, μ = 30/hour

    Mean waiting time in queue \(= \frac{\lambda }{{\mu \left( {\mu - \lambda } \right)}}\)

    Mean waiting time in queue \(= \frac{{20}}{{30\left( {30 - 20} \right)}}\)

    Mean waiting time in queue \(= \frac{{20}}{{300}} = \frac{1}{{15}}{\rm{\;hour}}\)

    ∴ Mean waiting time in queue \(= \frac{1}{{15}} \times 60\)

    Mean waiting time in queue = 4 minutes

  • Question 4
    1 / -0
    At a workstation, 6 jobs arrives every minute. The mean time spent on each job in the workstation is 1/10 minute. The mean steady state number of job in the system is ___________
    Solution

    Concept:

    No. of jobs in system, \({L_S} = \frac{\lambda }{{\mu - \lambda }}\)

    No. of jobs in queue, \({L_q} = \frac{{{\lambda ^2}}}{{\mu \left( {\mu - \lambda } \right)}}\)

    Calculation:

    Arrival rate λ = 6 jobs/minute

    Service rate, μ = 10 jobs/minute

    ∴ No. of jobs in system, \({L_S} = \frac{\lambda }{{\mu - \lambda }}\)

    \(\Rightarrow {L_S} = \frac{6}{{10 - 6}} = 1.5\)

    Points to remember

    • Average arrival time and the time spent in the system (Waiting time in system) = \({W_s} = \frac{1}{{\mu - \lambda }}\)
    • Average arrival time and the time spent in the queue (before being served) (Waiting time in queue) = \({W_q} = \frac{\lambda }{\mu }.\frac{1}{{\mu - \lambda }}\)
    • Average number of customers in the system = \({L_s} = \lambda {W_s} = \lambda .\frac{1}{{\mu - \lambda }}\)
    • Average number of customers in the queue = Average queue length = \({L_q} = \lambda {W_q} = \lambda .\frac{\lambda }{\mu }.\frac{1}{{\mu - \lambda }} = \frac{{{\lambda ^2}}}{\mu }\left( {\frac{1}{{\mu - \lambda }}} \right)\)
    • Probability that there are k customers in the system = (ρ)k(1 - ρ) = \(\frac{\lambda }{\mu }\left( {\frac{1}{{\mu - \lambda }}} \right)\)
    • Probability that there are more than k customers = \({\left( {\frac{\lambda }{\mu }} \right)^{k + 1}}\)
  • Question 5
    1 / -0
    In a factory, breakdown of machines occur at 3 machines/hour and breakdown time at one machine costs Rs. 60/hour. There are two choices for repairmen. Repairman ‘A’ demands Rs. 20/hour and repair machines at the rate of 4 per hour. While the repairman ‘B’ demands Rs. 30/hour and repair machines at 6 per hour. Which repairman should be hired and what will be cost
    Solution

    Case I: Repairman ‘A’

    λ = 3, μ = 4

    Average downtime of machine\({\rm{\;}} = \frac{1}{{\mu - \lambda }} = \frac{1}{{4 - 3}}\)

    Average downtime of machine = 1 hour

    Thus,

    Downtime of 3 machines that arrive in an hour = 3 × 1 = 3 hours

    Now,

    Total cost = Downtime cost + Repairman charges

    Total cost = (60 × 3) + (20 × 3)

    Total cost = Rs. 240

    Case II: Repairman B

    λ = 3, λ = 6

    Average downtime\(= \frac{1}{{\mu - \lambda }} = \frac{1}{{6 - 3}} = \frac{1}{3}\)

    Downtime of 3 machines that arrive in an hour\(= \frac{1}{3} \times 3 = 1\;hour\)

    Total cost = (60 × 1) + (30 × 1)

    Total cost = Rs. 90

    So, Repairman ‘B’ should be hired and total cost will be Rs. 90.

  • Question 6
    1 / -0
    In a facility, the jobs arrive at an average rate of 4 in a 12-hour shift. The arrival rate of jobs follow the Poisson distribution. The average service time follows exponential distribution and the average service time of a job on the facility is 60 minutes. What will be the idle time in hours of the facility per shift?
    Solution

    Concept:

    The idle time will be the product of the probability of no customers in the system and the shift duration.

    Probability of no customer is \({P_0} = 1 - \frac{\lambda }{\mu }\)

    Where λ and μ are the arrival and service rates

    Calculation:

    The arrival rate is:

    \(\lambda = \frac{4}{{12}} = \frac{1}{3}\;h{r^{ - 1}}\)

    Service rate is:

    \(\mu = 1\;h{r^{ - 1}}\)

    Thus:

    \({P_0} = 1 - \frac{1}{3} = \frac{2}{3}\)

    Idle time in hours:

    \(T = \frac{2}{3} \times \;12 = 8\;hours\)

Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Selfstudy
Selfstudy
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now