Self Studies

Construction Materials & Management Test 1

Result Self Studies

Construction Materials & Management Test 1
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    2 / -0.33
    If D is the duration, ES and EF are the earliest start time and earliest finish time, LS and LF are the latest start time and latest finish time, then the following relation(s) hold(s) good :
    A. EF = ES + D
    B. LS = LF – D
    C. D = EF – ES
    Select the code for the correct answer from the options given below :
    Solution

    Concept:

    In case of project management the followings are definition of various terms:

    Duration (D): Duration is the estimated or actual time required to complete a task or an activity.

    Earliest start time (ES): It is defined as the earliest possible time at which an activity can start. It is calculated by moving from first to last event in a network diagram.

    Earliest finish time (EF): It is the earliest possible time at which an activity can finish.

    Relationship between earliest start time, earliest finish time and duration is given by,

    Earliest finish time = Earliest start time + duration of that activity

    ∴ EF = ES + D

    EF - ES = D

    Latest start time (LS): It is defined as the latest time an activity can start and still allow the project to be completed on estimated project completion time.

    Latest finish time (LF): It is the latest possible time at which an activity can finish and still allow the project to be completed on estimated project completion time.

    Relationship between latest start time, latest finish time and duration is given by,

    Latest finish time = Latest start time + duration of that activity

    ∴ LF = LS + D

    ∴ Correct relationship is EF = ES + D.
  • Question 2
    2 / -0.33
    Purchasing cost of a new machine is 8 Lacs. Salvage value after expected life of 3 year is 1 Lacs. The rate of depreciation using constant rate of declining balance method is
    Solution

    Concept

     Fixed declining balance or Constant percentage method is given by 

    \(FDB = 1 - {\left( {\frac{{{C_S}}}{{{C_i}}}} \right)^{\frac{1}{n}}}\)

     Where Cs is Salvage or scrap value

     Ci is the initial cost of an asset

    Calculation

     Given, Cs = 1lac, Ci = 8 lac, n = 3 year

      \(\begin{array}{l} r\; = \;1 - {\left( {\frac{{{C_S}}}{{{C_I}}}} \right)^{\frac{1}{n}}}\; = \;1 - {\left( {\frac{1}{8}} \right)^{\frac{1}{3}}}\\ \; = \;1 - \frac{1}{2}\; = \;0.5 \end{array}\)

     

  • Question 3
    2 / -0.33

    Which of the following statements are true

    Solution

    Concept

    1) Normal consistency test

    Consistency: Vicat’s Apparatus is used to find out the consistency, initial setting time and final setting time of the cement. In the normal consistency test we have to find out the amount of water to be added to the cement to form a cement paste of normal consistency.

    Type of test

    Water to be added

    (Consistency)

    Setting time

    (both initial and final)

    0.85P

    Compressive strength test

    (P/4 + 3) %

    Soundness test

    0.78 P


    Important Point:

    Standard consistency is the consistency of the cement paste that permits the Vicat’s plunger of diameter 10 mm and height 50 mm to penetrate in to the mould up to depth of 33 to 35 mm from the top. 

    2) Low heat Cement

    This cement is manufactured by reducing the proportion of C3A and C3S and increasing the proportion of C2S. This cement shows a low rate of development of strength (Due to increasing C2S). This cement is used in mass concreting.

    Example - Hydraulic structures.

    3) Bogue compounds

    There are four compounds (Called Bogue's Compounds) formed as a result of hydration of cement:

    Bogue Compounds

    Dicalcium Silicate (C2S): This compound will undergo reaction slowly. It is responsible for the progressive strength of concrete. This is also called as Belite. 

    A higher percentage of C2S results in slow hardening, less heat of hydration, and great resistance to chemical attack.

    Tricalcium silicate (C3S): This is also called as Alite. It undergoes hydration within one week and helps in the development of strength in the early stages of concrete (aka hardening).

    It has the best cementitious property among all the other Bogue's Compounds. Tricalcium Silicate (C3S) hardens rapidly and is largely responsible for the initial set and early strength.

     The cement that has more C­­­­3S content is good for cold weather concreting.

    Tricalcium aluminate (C3A): Celite is the quickest one to react when the water is added to the cement. It is responsible for the flash setting. The increase of this content will help in the manufacture of Quick Setting Cement. 

    It provides weak resistance against sulphate attack and contribution to the development of strength is significantly less than above two bogue compounds.

    Tetra calcium Alumino ferrite (C4AF): This is called as Felite. The heat of hydration is 420 J/Cal. It has the poorest cementing value but it responsible for long term gain of strength of the cement.

  • Question 4
    2 / -0.33

    What is carbon content (%) in mild steel?

    Solution

    Steel is an alloy of iron and carbon, along with small amounts of other alloying elements or residual elements as well. The plain iron-carbon alloys (Steel) contain 0.002 - 2.1% by weight carbon. For most of the materials, it varies from 0.1-1.5%.

    There are 3 types of plain carbon steel:

    (i) Low-carbon steels: Carbon content in the range of < 0.3%

    (ii) Medium carbon steels: Carbon content in the range of 0.3 – 0.6%.

    (iii) High-carbon steels: Carbon content in the range of 0.6 – 0.8%.

    Hence the carbon content (%) in mild steel (Low-carbon steel) is < 0.3%, i.e 0.15 – 0.3%

  • Question 5
    2 / -0.33

    Consider the following data for concrete with mild exposure:

    Water-cement ratio = 0.50

    Water = 191.6 litre

    The required cement content will be

    Solution

    Concept:

    Water Cement ratio (W/C) is the ratio of weight of water to weight of cement in a concrete mix. This ratio decides the strength and workability of concrete.

    According to Abram’s law, the strength of a concrete mix is inversely related to the weight ratio of water to cement. Higher W/C ratio, lower the strength but higher is the workability.

    Calculation:

    \(\frac{W}{C} = 0.5 \Rightarrow C = \frac{W}{{0.5}}\)

    Volume of water = 191.6 litre = 0.1916 m3

    Mass of water = 0.1916 × 103 = 191.6 kg

    For 1 m3 cement content required is,

     \(C = \frac{{191.6}}{{0.5}} = 383.2 \;kg\)

  • Question 6
    2 / -0.33
    If creep coefficient for concrete at 7 days is k1 and at 28 days is k2 then
    Solution

    Concept

    See clause 6.2.5.1 of IS 456:2000, the strain that develops due to constant sustain loading is called creep strain but in the initial age of concrete, the creep strain of concrete is higher than later age.

    As per IS 456: 2000, Clause 6.2.5.1:

    Age at loading 

    Value of creep coefficient (θ)

    7 days

    2.2

    28 days

    1.6

    1 year

    1.1

     

    The effective modulus of elasticity is given by:

    \({E_{effective}} = \frac{{{E_c}}}{{1 + θ }}\)

    where,

    Ec = Modulus of elasticity of concrete

    However, elastic strain remains constant throughout. So the creep coefficient (θ ) \(= \frac{{Creep\;strain}}{{Elastic\;strain}},\) decrease with time.

  • Question 7
    2 / -0.33

    Which of the following sentences is CORRECT in the case of cement?

    Solution

    Option 1: Correct

    The following table shows the composition of cement and their properties.

    Ingredients

    Within limit

    If in excess

    Lime

    (62 – 65%)

    Controls strength and soundness

    Makes the cement unsound and it expands and disintegrate

    Silica

    (17 - 25 %)

     Adds strength to cement, as it forms C2S and C3S

    Causes slow setting of cement

    Alumina

    (3 - 8 %)

    Provides quick setting of cement and lowers the clinkering temp

    Lowers the strength

    Iron oxide

    (3 - 4 %)

    Provides color, hardness , strength and helps in fusion of raw material

     

    Magnesia

    (1 - 3 %)

    Provides hardness and color Decreases shrinkage

    Makes the cement unsound

    Alkalies

    (0.2 - 1 %)

    Should be in limit

    Alkali aggregate reaction

    Efflorescence and staining

    Sulphur trioxide

    (1-2%)

    Should be in limit

    Makes the cement unsound

    Reduces strength

     

    Option 2: Incorrect

    Alumina is responsible for flash set, not a false set. 
    False set is due to singenite K2Ca(SO4)2 and its plasticity can be regained by remixing without adding water in it. Basically, flash set means premature setting. 
    Flash set is due to Alumina, It induces permanent rigidity in concrete or mortar, plasticity of which cannot be regained by remixing. 

     

    Option 3: Incorrect

    Bouge’s Compound

    Percentage Composition

    Heat of Hydration

    Tricalcium silicate (Alite)

    40 – 60

    500 Joules/gm

    Dicalcium silicate (Belite)

    20 – 30

    250 Joules/gm

    Tricalcium aluminate (Celite)

    8 – 12

    800 Joules/gm

    Tetra calcium aluminoferrite (Felite)

    6 – 10

    420 Joules/gm

    the decreasing order of rate of hydration of Portland cement compounds is

    C4 AF > C3 A > C3 S > C2 S

    the decreasing order of heat of hydration of Portland cement compounds is

    C3 A > C3 S > C2 S > C4 AF

    Option 4: Incorrect

    C-H-S gel is mainly responsible for strength in cement. This is also known as Tubermorite gel. 

    Formula of C-H-S gel: CaO.H2O.SiO2

  • Question 8
    2 / -0.33
    The salvage value of any equipment is Rs.1000 and after five years of its use, its book value after two years of its useful life is Rs.6400. The original cost of the equipment is
    Solution

    Concept

    By Straight line method 

    Depreciation is given by 

    \({D_m} = \frac{{{C_i} - {C_s}}}{n}\)

    Where Dm is depreciation 

    Ci is the Initial cost or Original cost of an asset

    Cs is Salvage or scrap value (Estimated at the end of utility period)

    Book value (Bm) at the end of 'm ' years life is given by 

    \({B_m} = {C_i} - m × {D_m}\)

    Calculation

    Let the original cost (Ci) of the equipment be Rs. P

    Annual depreciation (Dm\(= \;\frac{{P - Salvage value}}{5}\)

      \(= \;\frac{{P - 1000}}{5}\)

    Book value at the end of 2 year

    \(\begin{array}{l} \; = \;P - 2 \times \frac{{\left( {P - 1000} \right)}}{5}\\ \therefore P - \frac{{2\left( {P - 1000} \right)}}{5}\; = \;6400 \end{array}\)

    P = Rs.10000
  • Question 9
    2 / -0.33

    Consider the following forms of water in a hydrated cement paste:

    1. Capillary water

    2. Chemically combined water

    3. Interlayer water

    4. Adsorbed water

    Which of the above forms of water will on its/their removal, cause shrinkage of the paste?
    Solution

    Concept:

    Shrinkage in concrete: It can be defined as a decrease in either length or volume of concrete material resulting from changes in moisture content or chemical changes. Shrinkage is time-dependent and its value includes plastic shrinkage, autogenous shrinkage, drying shrinkage.

    • Plastic shrinkage is contraction in volume due to water movement from the concrete while still in the plastic state or before it sets. Loss of water by evaporation from the surface of the concrete in different layers or by the absorption by aggregate or subgrade is believed to be the reasons of plastic shrinkage.
    • Drying shrinkage is contraction in volume due to loss in moisture from the concrete while drying. It is the loss of capillary water and water held in gel pores that cause the change in the volume.
    • Autogenous shrinkage is the change in volume due to the chemical process of hydration of cement, exclusive of effects of applied load, and change in either thermal condition or moisture content.

    Thus, the cause of shrinkage in hydrated cement paste is due to the removal of moisture in the form of capillary water, interlayer water, and adsorbed water. The chemically combined water does not take part in shrinkage and cannot be removed by the process of shrinkage.

  • Question 10
    2 / -0.33

    For increasing the workability of concrete, it is necessary to

    1. Increase the quantity of Sand

    2. Decrease the quantity of sand

    3. Use Rounded aggregate

    4. Alter the proportion of fine and coarse aggregates

    Which of the following statements are correct

    Solution

    Concept

    Factors Affecting workability are as follows

    Factors affecting the workability of concrete

    Key points

    Water content

    It is generally expressed in terms of the water-cement ratio.

    High water content indicates a high workability of concrete and vice versa.

    Rich mix proportion

    Rich mix has sufficient cement aggregates, hence it will have a proper lubrication, thus increasing workability.

    Aggregate/cement ratio

    Higher the ratio, Leaner the concrete, and lesser the workability. Lower the ratio gives cohesive and fatty mix with better workability.

    Size of aggregate

    Aggregate with Finer particles have more surface area, hence requires more water to make it workable.

    Aggregate with coarser particles requires less water to make it workable.

    Hence for fixed water content large-sized particles are more workable.

    Shape of aggregate

    The irregular shape of aggregate requires more water to make it workable, due to greater surface area.

    Rounded shape aggregate requires less water to make it workable, due to less surface area.

    Hence for fixed water content rounded aggregate has more workability.

    Temperature

    High temperature reduces the workability of concrete and increases the slump loss.

    Use of admixtures

    Admixtures such as air-entraining admixtures increase the workability of concrete.

  • Question 11
    2 / -0.33

    The time estimates in days are obtained from four contractors P, Q, R, S for executing a particular job are as under

    Contractor

    Optimistic time

    (t0)

    Most likely time

    (tm)

    Pessimistic time

    (tP)

    P

    5

    10

    13

    Q

    6

    9

    12

    R

    5

    10

    14

    S

    4

    10

    13

    Solution

    Concept

    Certainty of project can be determined by comparing standard deviation

    Standard deviation (σ ) is given by,

    \(\sigma = \frac{{{t_p} - {t_o}}}{6}\)

    Expected completion of time (tE) is given by

    \({t_E} = \frac{{{t_o} \;+ \;4\; \times \;{t_m} \;+ \;{t_p}}}{6}\)

    Where, tp is pessimistic time

    tm is most likely time

    to is optimistic time

    Calculation

    Given,

    For contractor P (t0) = 5, (tm) = 10, (tP) = 13

    Standard deviation \(\sigma = \frac{{{t_p} - {t_o}}}{6} = \frac{{13 - 5}}{6}\) = 1.33

    Expected time (TE) = \(\frac{{{t_o}\; + \;4\; \times\; {t_m}\; + \;{t_p}}}{6} = \frac{{5\; + \;4 \;\times \;10\; + \;13}}{6}\) = 9.67

    For contractor Q (t0) = 6, (tm) = 9, (tP) = 12

    Standard deviation \(\sigma = \frac{{{t_p} - {t_o}}}{6} = \frac{{12 - 6}}{6}\) = 1

    Expected time (TE) = \(\frac{{{t_o}\; + \;4\; \times\; {t_m}\; +\; {t_p}}}{6} = \frac{{6\; + \;4\; \times\; 9\; + \;12}}{6}\) = 9

    For contractor R (t0) = 5, (tm) = 10, (tP) = 14

    Standard deviation \(\sigma = \frac{{{t_p} - {t_o}}}{6} = \frac{{14 - 5}}{6}\) = 1.5

    Expected time (TE) = \(\frac{{{t_o}\; + \;4\; \times \;{t_m}\; + \;{t_p}}}{6} = \frac{{5\; + \;4\; \times \;10\; + \;14}}{6}\) = 9.833

    For contractor S (t0) = 4, (tm) = 10, (tP) = 13

    Standard deviation \(\sigma = \frac{{{t_p} - {t_o}}}{6} = \frac{{13 - 4}}{6}\) = 1.5

    Expected time (TE) = \(\frac{{{t_o}\; + \;4\; \times\; {t_m}\; + \;{t_p}}}{6} = \frac{{4\; +\; 4 \;\times \;10\; + \;13}}{6}\) = 9.5

    Since the time estimate of Contractor Q has least standard deviation (i.e. 1). So work can be completed by him in most certain manner.

  • Question 12
    2 / -0.33
    A construction equipment was purchased in Rs. 12000. Assuming its salvage value at the end of 6 years to be Rs. 3000, and annual sinking percentage is 4%. Determine the difference of the amount of depreciation (in rupees) determined by straight-line method and sinking fund method for each year.
    Solution

    For straight-line method:

    Depreciation is given by:

    \({\rm{D}} = \frac{{{\rm{P}} - {\rm{S}}}}{{\rm{n}}} = \frac{{12000 - 3000}}{6} = \frac{{9000}}{6} = Rs.\;1500/ - \)

    For sinking fund method:

    A = annual sinking fund to replace = 12000 - 3000 = Rs. 9000

    \(\rm{\therefore {\rm{D}} = \frac{{9000 \times 0.04}}{{{{\left( {1 + 0.04} \right)}^6} - 1}} = Rs.{\rm{\;}}1356.50/ - }\)

    ∴ Difference = 1500 - 1356.50 = Rs. 143.50/-
  • Question 13
    2 / -0.33

    Match the following:

    A)

    Cost plus percentage rate contract

    i)

    Unit Price contract

    B)

    Labour contract

    ii)

    Above or below percent

    C)

    Percentage Rate contract

    iii)

    Actual cost plus added percentage

    D)

    Item Rate contract

    iv)

    Labour cost excluding materials

    Solution

    Item Rate contract

    Items rate contract is also known as Unit Price contract or Schedule contract. A contractor undertakes the execution of work on an item rate basis. He is required to quote rate for individual item of work on the basis of schedule of quantities (i.e., Bill of Quantities) furnished by the department. The amount to be received by the contractor, depends upon the quantities of work actually performed. 

    Percentage Rate Contract

    In this form of contract, the department draws up ‘item rate tender’ i.e., Bill of quantities with – rate, amount and total amount. The contractors are required to offer to carry out the work as per with the rates shown in the specific price schedule or some percentage above or some percentage below the rates indicated in the schedule of work attached with the tender.

    Lump – sum Contract

    In this type of contract, contractor is required to quote a fixed sum for execution of work complete in all respect in the stipulated time according to the drawing, design and specification supplied to him with the tender.

    Labour contract

    In labour contact, the contractor undertakes contract for the labour portion only excluding the materials which are arranged and supplied at the work site by the department / owner. The contractor engages the requisite labour and gets the work done as per drawings and specifications. It is an items rate basis for labour portion only and the contractor is paid for the quantities of work done on measurement of different items of work at the stipulated rate in the contract agreement.   

    Material supply contract

    In this type of contract, a contractor has to offer his rates for supply of the required quantities of materials, inclusive of all local taxes, carriage and delivery charges to the specified stores within the time limit prescribed in the tender. All such materials received should be examined and counted or measured, as the case may be, when delivery is taken. 

    Cost plus percentage rate contract

    In this type of contract, a contractor agrees to take the work of construction on the actual of work plus on agreed percentage in addition, for his services. It is generally adopted when the labour and material cost are liable to fluctuate heavily in the market.
  • Question 14
    2 / -0.33

    A PERT network diagram in the form of a line diagram with optimistic time, pessimistic time and most likely time of the activity are given below in the table:

    ActivityOptimistic TimePessimistic TimeMost Likely Time
    P - Q4107
    Q - R6108
    R - S91515
    S - T8118

     

    All the data in the table are in days. The Probable range of total duration will be

    Solution

    Concept:

    The expected completion time (tE)

    \({t_E} = \frac{{{t_0} + 4{t_L} + {t_P}}}{6}\)

    Variance = \([\frac{{t_p - t_o}}{6}]^2\)

    Where,

    t0 = optimistic time

    tL = most likely time

    tP = pessimistic time

    The probable range is from \((t_e - 3\sigma)\; to\;(t_e + 3\sigma)\)

    Solution:

    \(\begin{array}{l} {t_P}_Q = \frac{{4\; + \;4 \;\times\; 7 \;+ \;10}}{6} = 7\\ {t_{{QR}}} = \frac{{6 \;+ \;4 \;\times \;8 \;+ \;10}}{6} = 8 \end{array}\)

    \(\begin{array}{l} {t_{RS}} = \frac{{9\; + \;4 \;\times\; 15 \;+ \;15}}{6} = 14\\ {t_{{ST}}} = \frac{{8 \;+ \;4 \;\times \;8 \;+ \;11}}{6} = 8.5 \end{array}\)

    ActivityExpected Time (te)Variance
    PQ71
    QR80.44
    RS141
    ST8.50.25
    Total37.52.69

     

    Standard Deviation, \(\sigma = \sqrt{2.69} = 1.64\)

    The probable range is from ​\((37.5 - 3\times1.64)\; to\;(37.5 + 3\times1.64)\)

    Hence, the Probable range is from 32.58 to 42.42

  • Question 15
    2 / -0.33

    By using a mix design procedure, mix proportions for the desired grade of concrete have been obtained as 1 : 2.2 : 3.6 (by mass) with water cement ratio of 0.55. To make 0.40 m3 of concrete the weight of cement required is ______kg.

    Assume air content to be 0% and specific gravity of cement, sand and aggregate were 3.15, 2.65 and 2.7 respectively.
    Solution

    Calculations

     let weight of cement = x kg

     weight of sand = y kg

     weight of aggregate = z kg

     x : y : z = 1 : 2.2 : 3.6

    \(\begin{array}{l} \frac{{\rm{x}}}{{\rm{y}}} = \frac{1}{{2.2}}\\ \frac{{\rm{x}}}{{\rm{z}}} = \frac{1}{{3.6}} \end{array}\)

    Volume of concrete = Vw + Vs

    \(0.40{\rm{\;}} = {\rm{\;}}\frac{{{\rm{weight\;of\;water}}}}{{{\rm{Density\;of\;water}}}} + \frac{{{\rm{weight\;of\;solids}}}}{{{\rm{Density\;of\;solids}}}}\)

    \({\rm{water\;cement\;ratio}} = \frac{{{\rm{weight\;of\;water}}}}{{{\rm{weight\;of\;cement}}}}\)

    0.55 x = WW

    \(0.40 = \frac{{0.55{\rm{x}}}}{{1000}} + \left[ {\frac{{\rm{x}}}{{{{\rm{G}}_{\rm{c}}} \times 1000}}} \right] + \frac{{\rm{y}}}{{{{\rm{G}}_{\rm{s}}} \times 1000}} + \frac{{\rm{z}}}{{{{\rm{G}}_{\rm{a}}} \times 1000}}\)

    \(400{\rm{\;}} = {\rm{\;}}0.55{\rm{x\;}} + {\rm{\;}}\frac{{\rm{x}}}{{{{\rm{G}}_{\rm{c}}}}} + \frac{{\rm{y}}}{{{{\rm{G}}_{\rm{s}}}}} + \frac{{\rm{z}}}{{{{\rm{G}}_{\rm{a}}}}}\)

    Gc = 3.15

    Gs = 2.65

    Ga = 2.7

    y = 2.2 x

    z = 3.6 x

    \(\begin{array}{l} 400 = 0.55{\rm{x}} + \frac{{\rm{x}}}{{3.15}} + \frac{{2.2{\rm{x}}}}{{2.65}} + \frac{{3.6{\rm{x}}}}{{2.7}}\\ 400 = {\rm{x}}\left[ {\frac{0.55}{{1}}+\frac{1}{{3.15}} + \frac{{2.2}}{{2.65}} + \frac{{3.6}}{{2.7}}} \right] \end{array}\)

    x = 131.97 kg

    So weight of cement required is 132 kg
Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now