  • Question 1
    2 / -0.33

    If D is the duration, ES and EF are the earliest start time and earliest finish time, LS and LF are the latest start time and latest finish time, then the following relation(s) hold(s) good :
    A. EF = ES + D
    B. LS = LF – D
    C. D = EF – ES
    Select the code for the correct answer from the options given below :

  • Question 2
    2 / -0.33

    Purchasing cost of a new machine is 8 Lacs. Salvage value after expected life of 3 year is 1 Lacs. The rate of depreciation using constant rate of declining balance method is

  • Question 3
    2 / -0.33

    Which of the following statements are true

  • Question 4
    2 / -0.33

    What is carbon content (%) in mild steel?

  • Question 5
    2 / -0.33

    Consider the following data for concrete with mild exposure:

    Water-cement ratio = 0.50

    Water = 191.6 litre

    The required cement content will be

  • Question 6
    2 / -0.33

    If creep coefficient for concrete at 7 days is k1 and at 28 days is k2 then

  • Question 7
    2 / -0.33

    Which of the following sentences is CORRECT in the case of cement?

  • Question 8
    2 / -0.33

    The salvage value of any equipment is Rs.1000 and after five years of its use, its book value after two years of its useful life is Rs.6400. The original cost of the equipment is

  • Question 9
    2 / -0.33

    Consider the following forms of water in a hydrated cement paste:

    1. Capillary water

    2. Chemically combined water

    3. Interlayer water

    4. Adsorbed water

    Which of the above forms of water will on its/their removal, cause shrinkage of the paste?

  • Question 10
    2 / -0.33

    For increasing the workability of concrete, it is necessary to

    1. Increase the quantity of Sand

    2. Decrease the quantity of sand

    3. Use Rounded aggregate

    4. Alter the proportion of fine and coarse aggregates

    Which of the following statements are correct

  • Question 11
    2 / -0.33

    The time estimates in days are obtained from four contractors P, Q, R, S for executing a particular job are as under

    Contractor

    Optimistic time

    (t0)

    Most likely time

    (tm)

    Pessimistic time

    (tP)

    P

    5

    10

    13

    Q

    6

    9

    12

    R

    5

    10

    14

    S

    4

    10

    13

  • Question 12
    2 / -0.33

    A construction equipment was purchased in Rs. 12000. Assuming its salvage value at the end of 6 years to be Rs. 3000, and annual sinking percentage is 4%. Determine the difference of the amount of depreciation (in rupees) determined by straight-line method and sinking fund method for each year.

  • Question 13
    2 / -0.33

    Match the following:

    A)

    Cost plus percentage rate contract

    i)

    Unit Price contract

    B)

    Labour contract

    ii)

    Above or below percent

    C)

    Percentage Rate contract

    iii)

    Actual cost plus added percentage

    D)

    Item Rate contract

    iv)

    Labour cost excluding materials

  • Question 14
    2 / -0.33

    A PERT network diagram in the form of a line diagram with optimistic time, pessimistic time and most likely time of the activity are given below in the table:

    ActivityOptimistic TimePessimistic TimeMost Likely Time
    P - Q4107
    Q - R6108
    R - S91515
    S - T8118

     

    All the data in the table are in days. The Probable range of total duration will be

  • Question 15
    2 / -0.33

    By using a mix design procedure, mix proportions for the desired grade of concrete have been obtained as 1 : 2.2 : 3.6 (by mass) with water cement ratio of 0.55. To make 0.40 m3 of concrete the weight of cement required is ______kg.

    Assume air content to be 0% and specific gravity of cement, sand and aggregate were 3.15, 2.65 and 2.7 respectively.

Submit Test
Self Studies
User
Question Analysis
  • Answered - 0

  • Unanswered - 15

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
Submit Test
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now