Self Studies
Selfstudy
Selfstudy

Construction Materials & Management Test 2

Result Self Studies

Construction Materials & Management Test 2
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    1 / -0
    The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will be
    Solution

    Concept

    Indirect project Cost: Indirect project cost re those expenditures which cannot be clearly allocated to the individual activities of the project, but are assessed as a whole.

    The indirect cost rises with an increase in duration. 

    Direct Project Cost: These include labour cost, material cost, equipment cost etc.

    Direct cost decreases with increase in duration.

    Note: Here the activity duration is crashed i.e. Reducing activity duration (from 25 to 22 days)

    ∴ Indirect cost decreases as time is decreasing

    Direct cost increases

    Calculation

    Given,

    Normal activity duration = 25 days

    Crash activity duration = 22 days

    Cost slope = 1500/- , Indirect cost = 1000/- per day

    Normal cost of activity = 50,000 /-

    No. of days crashed = 25 - 22 = 3 days. 

    The increase in direct cost for 3 days crashing

    = Cost Slope × 3

    \(1500× 3\)

    = 4500 rupees

    The decrease in indirect cost for 3 days

    \(1000× 3\)

    = 3000 rupees

    Total project cost = Direct cost + Indirect cost

    The total cost of the activities after crashing

    =  50000 + 4500 - 3000

    = 51500 rupees

    ∴ Total cost = 51,500 /-

     

  • Question 2
    1 / -0
    The original cost of equipment is rupees 1,00,000. Its salvage value at the end of its useful life of five years is 40,000. Its book value at the end of two years of its useful life as per straight line method of evaluation of depreciation will be
    Solution

    Concept

    By Straight line method 

    Depreciation is given by 

    \({D_m} = \frac{{{C_i} - {C_s}}}{n}\)

    Where Dm is depreciation 

    Ci is Initial cost of an asset

    Cs is Salvage or scrap value (Estimated at the end of utility period)

    Book value (Bm) at the end of 'm ' years life is given by 

    \({B_m} = {C_i} - m × {D_m}\)

    Calculation

    Given,

    Ci = 1,00,000 /-, Cs = 40,000 /- 

    n = 5 years

    Depreciation is 

    \({D_m} = \frac{{1,00,000 - 40000}}{5} = 12,000\)

    Book value at the end of 2 years of lifetime is given by

    \({B_m} = {C_i} - m × {D_m}\)

    = 1,00,000 - 2 × 12,000

     = 76,000 /-

     

     

  • Question 3
    1 / -0
    A contract in which the contractor is required to quote a fixed sum for execution of the complete work by referring to the drawing, designs and specifications is known as a __________.
    Solution

    Item rate contract: It is also known as unit-price contract or schedule contract. For such contracts, contractors are required to quote rates for individual items of work on the basis of schedule of quantities furnished by the department. This type of contract is followed by Central Public works and Railway departments.

    Lump-Sum Contract: In this form of contract, the contractors are required to quote a fixed sum for execution of a work complete in all respect i.e. according to the drawing, designs and specifications supplied to them with the tender within the specified time.

    The departmental schedule of rates for various items of work are also provided which regulates the payment to the contractor in respect of the items of works involved for any additions and alterations not covered by the original work.

    Price Work Agreement: It is type of contract in which the rate is agreed upon without reference to the total quantity of work to be done or the quantity of work to be done within a given period. But the detailed specifications and the total cost of the whole work to be done are mentioned.

    There is no security money and penalty clause and it is usually adopted for urgent small work and may be taken up for execution without inviting tender and a reasonable time is saved.

    Target contract: It is the type of contract where the contractor is paid on a cost-plus percentage basis for work performed under this contract, and in addition he receives a percentage plus or minus on savings or excess effected against either a prior agreed estimate of total cost or a target value arrived at by measuring the work on completion and valuing prior agreed rates.
  • Question 4
    1 / -0
    The optimistic, most likely and pessimistic time estimates of activity are 8, 15 and 18 weeks respectively. The Probable range of completion time of the activity will be
    Solution

    Concept:

    The expected completion time (tE)

    \({t_E} = \frac{{{t_0} + 4{t_L} + {t_P}}}{6}\)

    Variance = \([\frac{{t_p - t_o}}{6}]^2\)

    Where,

    t0 = optimistic time

    tL = most likely time

    tP = pessimistic time

    The probable range is from \((t_e - 3\sigma)\; to\;(t_e + 3\sigma)\)

    Solution:

    The expected completion time (tE)​

    \(\begin{array}{l} \therefore {t_E} = \frac{{8\; + \;4 \;\times\; 15 \;+ \;18}}{6} \\ {t_E} = 14.33\;weeks \end{array}\)

    Variance = \([\frac{{18 - 8}}{6}]^2 = 2.78\;weeks\)

    Standard Deviation, \(\sigma = \sqrt{2.78} = 1.67\;weeks\)

    The Probable range of completion time of the activity will be from \((t_e - 3\sigma)\; to\;(t_e + 3\sigma)\)

    i.e. \((14.33 - 3\times1.67)\; to\;(14.33 + 3\times1.67)\)

    \(9.32\;weeks\; to\;19.34\;weeks\)

  • Question 5
    1 / -0
    A crane is purchased now, its useful life is 8 years after which a new crane must be purchased. If the interest rate is 6%, the capital recovery factor (CRF) up to 2 decimal places is
    Solution

     

    Concept

    Capital Recover Factor is given by 

    \(\frac{{i \times {{\left( {1 + i} \right)}^n}}}{{{{\left( {1 + i} \right)}^n} - 1}}\)

    Where,

    i is the annual interest rate and

    n is the number of annual interest periods

    Calculation

    Given,

     i = 6 % , n = 8 years

    \(CRF = \frac{{{{\left( {1 + i} \right)}^n}i}}{{{{\left( {1 + i} \right)}^n} - 1}} = \frac{{{{\left( {1 + 0.06} \right)}^8} \times \left( {0.06} \right)}}{{{{\left( {1 + 0.06} \right)}^8} - 1}} \Rightarrow 0.16\)

     

  • Question 6
    1 / -0

    For the following detail of the network, which of the following activity should be crashed first?

    Activity

    Normal duration (weeks)

    Normal cost (Rs.)

    Crash duration (weeks)

    Crash cost (Rs.)

    1 - 2

    4

    4000

    2

    12000

    2 - 3

    5

    3000

    2

    7500

    2 - 4

    7

    3600

    5

    6000

    3 - 4

    4

    5000

    2

    10000

    Solution

    Concept:

    In Crashing 

    The first step is to find the critical path 

    then, the Cost slope of all activities in the critical path is calculated.

    Activity with minimum cost slope is required to crash first.

    \({\rm{Cost\;slope}} = \frac{{{\rm{Crash\;cost}} - {\rm{Normal\;cost}}}}{{{\rm{Normal\;time}} - {\rm{Crash\;time}}}}\)

    \(∴ {\rm{CS}} = \frac{{{{\rm{C}}_{\rm{c}}} - {{\rm{C}}_{\rm{n}}}}}{{{{\rm{t}}_{\rm{n}}} - {{\rm{t}}_{\rm{c}}}}} = \frac{{{\rm{\Delta C}}}}{{{\rm{\Delta t}}}}\)

    Calculation:

    Activities

    ΔC (₹)

    Δt (weeks)

    Cost slope ₹ /week

    1 - 2

    12000 - 4000 = 8000

    4 - 2 = 2

    4000

    2 - 3

    7500 - 3000 = 4500

    5 - 2 = 3

    1500

    2 - 4

    6000 - 3600 = 2400

    7 - 5 = 2

    1200

    3 - 4

    10000 - 5000 = 5000

    4 - 2 = 2

    2500

     

    For network 1-2, 2- 4 duration is 11 days

    ∴ The critical path for the given network is 1 - 2, 2 - 3 and

    3 - 4 i.e. 13 days.

    ∴ Although the cost slope is minimum for activity 2 - 4 (but not in a critical path ),

    ∴ The activity to be crashed first is 2 - 3.

  • Question 7
    1 / -0

    Identify the correct Statements in accordance with PERT and CPM.

    Solution

    Concept:

    PERT approach takes account of the uncertainties. In this approach, 3 - time values are associated which each activity. So it is probabilistic.

    Whereas CPM involves the critical path which is the largest path in the network from starting to end event and defines the minimum time required to complete the project. So it is deterministic.

    CPM

    PERT

    CPM is an activity-oriented network diagram

    PERT is an event-oriented network diagram

    CPM is based upon a deterministic approach

    It is based on Probabilistic approach

    Only one time estimates are made for each activity

    Three-time estimates are made for each activity

    Each activity follows a normal distribution

    Each activity follows β distribution

     

     

Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now