  • Question 1
    3 / -1

    Mayank can do 50% more work than Shishu in the same time. Shishu alone can do a piece of work in 30 hours. Shishu starts working and he had already worked for 12 hours when Mayank joins him. How many hours should Shishu and Mayank work together to complete the remaining work?

    Solution

  • Question 2
    3 / -1

    A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn, i.e., first day A does it alone, second day B does it alone and 3rd day C does it alone. After that the cycle is repeated till the work is finished. They get Rs 240 for this job. If the wages are divided in proportion to the work each had done. Find the amount A will get?

    Solution

     .

  • Question 3
    3 / -1

    Read the passage below and solve the questions based on it.
    The tank at a water supply station is filled with water by several pumps. At first three pumps of Ihe same capacity are turned on: 2.5 hours later, two more pumps (both the same) of a different capacity are set into operation. After 1 hour, the additional pumps were set into operation; the tank was almost filled to its capacity (15 in 3 were still lacking): in another hour the tank was full. One of the two additional pumps could have filled the tank in 40 hours

    Q.

    What is the volume of the tank?

    Solution

     

    Let us assume that, first three pumps fills the tank in x hours .

    so,

    → Efficiency of each pump = (1/x) m³ / hour .

    then,

    → Efficiency of three pump = (3/x) m³ / hour .

     

    now,

    → First three pumps works for = 2.5h + 1h + 1h = 4.5 hours.

     

    so,

    → Water filled by 3 pumps in 4.5 hours = 4.5 * (3/x) = (13.5/x) m³ .

     

    now, given that,

    → Time taken by additional pump to fill the tank = 40 hours.

    so,

    → Efficiency of 2 additional tanks = 2 * (1/40) = (1/20) m³ / h .

     

    and,

    → Additional pumps work for = 1 + 1 = 2 hours.

     

    so,

    → Water filled by additional pumps in 2 hours = 2 * (1/20) = (1/10) m³ .

     

    therefore,

    → (13.5/x) + (1/10) = 1

    → (13.5/x) = 1 - (1/10)

    → (13.5/x) = (9/10)

    → x = 135/9 = 15 hours.

     

    since given that, in last 1 hour they filled 15 m³ .

     

    hence,

    → 3 * (1/15) + (1/20) = 15 m³

    → (1/5) + (1/20) = 15

    → (4 + 1)/20 = 15

    → (5/20) = 15

    → (1/4) = 15

    → 1 = 60  (Ans.) (Option A)

  • Question 4
    3 / -1

    Read the passage below and solve the questions based on it.

    There are three taps A, B and C and an outlet pipe D. A, B and C can fill the tank in the Panikam locality in 10, 20 and 25 h respectively. The outlet pipe can empty the same tank in 100 h. There are 2,000 houses in the locality. The tank has a capacity of 50,000 litres

    Q.

    If all the taps and the outlet pipe are opened simultaneously, how much water is thrown into the tank every hour?

    Solution

    Total time required to fill the tank: 1/10 + 1/20 + 1/25 - 1/100 = 18/100
    Time required to fill the tank in 1hr = capacity/total time
    = 50000*18/100
    = 9000litre

  • Question 5
    3 / -1

    Read the passage below and solve the questions based on it

    There are three taps A,B,C and an outlet pipe D. A, B and C can fill the tank in the Panikam locality in 10, 20 and 25 h respectively. The outlet pipe can empty the same tank in 100 h. There are 2,000 houses in the locality. The tank has a capacity of 50.000 litres

    Q. If the average requirement of every house in the area per day is 40 litres, for how many h, for the second time should the taps be opened? (Consider that all the three taps were opened on both occasions).

    Solution

  • Question 6
    3 / -1

    Refer to the data below and answer the questions that follow.

    Anoop and Sandeep can dig a well each in 10 and 5 days respectively. But on a particularly difficult terrain the work is such that due to fatigue every' subsequent day the efficiency of a worker falls by 10%.
    Q.If Anoop is given a task of digging one such well in the difficult terrain, then in how many days will he finish the work?

    Solution

    Correct Answer :- d

    Explanation : The total no. of days in which Anoop can dig the well is 10 days.

    Anoop's one day efficiency is 10%.

    On day one Anoop performs 10% of his work efficiency, then the next day he won't be able to perform because as per the question the efficiency of a worker falls by 10%.

    thus, 10%-10% = 0.

  • Question 7
    3 / -1

    A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

    Solution

    (A+B)'s one day's work = 1/3 part
    (A+B) works 2 days together = 2/3 part
    Remaining work = 1−2/3 = 1/3 part

    1/3 part of work is completed by A in two days
    Hence, one day's work of A = 1/6
    Then, one day's work of B = 1/3−1/6 = 1/6
    So, B alone can complete the whole work in 6 days.

  • Question 8
    3 / -1

    Refer to the data below and answer the questions that follow.

    Anoop was writing the reading comprehension sections in Lhe DOG entrance examinations, There were four passages of exactly equal length in terms of number of words and die four passages had 5, 8, 8 and 6 questions following each of them respectively. It is known that Anoop can answer exactly 12 questions in the time he takes to read any one of the four passages. Assume that his rate of reading and answering questions remains the same throughout the section.

    Q.

    By what per cent should Anoop increase his reading speed if he has to cut down on his total time spent on the section by 20%? Assume that the time spent on answering the questions is constant and as given in the directions.

    Solution

  • Question 9
    3 / -1

    A can work half as fast as B and C together. A and B together can work three times as fast as C. If all three of them complete a job in 15 days, how long would C take to complete the same work?

    Solution

    Let us assume that

    A finishes the work alone in a days

    B finishes the work alone in b days

    C finishes the work alone in c days

    So according to the question,

     

  • Question 10
    3 / -1

    In what time would a cistern be filled by three pipes of diameter of 1 cm, 2 cm and 3 cm if the largest pipe alone can fill the cistern in 49 minutes, the amount of water flowing through each pipe being proportional to the square of its diameter?

    Solution

    Since the amount of water flowing through each pipe is proportional to square of its diameter so if efficiency of longest pipe (3 cm) = 1/49

    Then efficiency of pipe (2 cm) = 4/(49 x 9)

    and efficiency of pipe (1 cm) = 1/ (49 x 9) 

    Now let cistern is filled by all three pipes in x minutes.

  • Question 11
    3 / -1

    Sagar is 20% more efficient than Pranesh. If Pranesh can complete a piece of work in 30 days, then in how many days can both Sagar and Pranesh complete the work?

    Solution

  • Question 12
    3 / -1

    A factory manufactures dyes. It has 12 men and two machines which can be operated by all of its men. It takes 4 hours to manufacture one dye on the machine with the operator. The machines can work continuously without a break. Without the machine each of the men can manufacture a dye in 8 hours. The policy is such that the production is maximized and the men are ready to work in three shifts of 8 hours per day. What will be the average cost incurred per dye if 1 man hour costs Rs 20 and 1 machine hour costs Rs 15?

    Solution

    To maximize the production, four men will work in each shift. 2 men will work with machines and 2 men work alone.
    Total cost incurred in one hour

  • Question 13
    3 / -1

    A, B, C, D and E are five taps. The capacity of B is 2 times that of A, the capacity of C is 3 times that of A. Capacities of D and E are 4 and 5 times that of A respectively. In the first case A, C and E act as input pipes and B and D act as output pipes.In the second case, C, D, E act as input pipes and A and B act as output pipes.If A and B working together as input pipes can fill the tank in 4 hours, then what is the difference in the time required to fill the tank in the first and second case stated above?

    Solution

    Let B take x hours to fill the tank, so according to the question, time required by each, 

    A = 2x 
    B=  x 
    C= 2x/ 3 
    D= 2x/4
    E= 2x/5

    A and B together fills the tank in 4 hours. 

    => 1/2x +  1/ x = 1 /4 

    =>  x = 6 

    In first case, when A, C and E act as input pipes and B and D as output pipes;

    Total time = 1/ 12 + 1/ 4 + 5/ 12 -1/ 6 - 1/ 3 

    => 4 hours

    In 2 nd case, when C, D and E act as input pipes and A and B  as output pipes;

    Total Time = ¼ + ⅓ +5/12- 1/12-⅙-⅓

    => 4/3 hours

    Difference = 4-4/3 = 4-4/3 = 8/3h

  • Question 14
    3 / -1

    Anil, Bhuvan and Chandan take 10,20 and 25 days to complete a job. What is the minimum time required to finish the job if not more than 2 of them work together on a single day and no two consecutive days have the same pair of people working?

    Solution

    Assume total amount of work = 100 units.
    A does = 10 units/day, B does = 5 units/day, and C does = 4 units/day
    Possible Pairs:
    A+B = 15 units/day, A+C = 14 units/day, B+C = 9 units/day
    To minimize time, we will use the first two pairs.
    So, 15 +14 +15 + 14 + 15 +14 + 15 = 102 units.
    So, little less than 7 days are required

    Hence, the correct option is 'B'.

  • Question 15
    3 / -1

    Anuj can do a piece of work in a certain number of days. To do the same piece of work, Bhanu takes thrice the number of days as Anuj takes whereas Chandu takes thrice as many days as Bhanu does and Dodo takes thrice as many days as Chandu does. Now, they are paired and two groups are formed. The first pair takes one-third the time taken by the second pair to complete the work, which is the first pair?

    Solution

    Let Anuj do the work in x days.

     So, Bhanu = 3x days, Chandu = 9x days and Dodo = 27x days

    Now, using options,

    Anuj + Chandu = 1/x + l/9x = 10/9x,

    So, they take 9x/10 days

    Bhanu + Dodo = l/3x + 1/27x = 10/27x, So, they take 27x/10 days

    Now, 1/3 of 27x/ 10 = 9x /10.

     So, Anuj and Chandu is first pair.

Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now