Self Studies

Linear Programm...

TIME LEFT -
  • Question 1
    1 / -0

    The objective function $$z = 4x_{1} + 5x_{2}$$, subject to $$2x_{1} + x_{2}\geq 7, 2x_{1} + 3x_{2} \leq 15, x_{2}\leq 3, x_{1}, x_{2} \geq 0$$ has minimum value at the point.

  • Question 2
    1 / -0

    The objective function of LPP defined over the convex set attains its optimum value at

  • Question 3
    1 / -0

    The constraints
    $$-{ x }_{ 1 }+{ x }_{ 2 }\le 1$$
    $$-{ x }_{ 1 }+3{ x }_{ 2 }\le 9$$
    $${x}_{1},{x}_{2}\ge 0$$ defines on

  • Question 4
    1 / -0

    An article manufactured by a company consists of two parts $$X$$ and $$Y$$. In the process of manufacture of the part $$X$$. $$9$$ out of $$100$$ parts may be defective. Similarly $$5$$ out of $$100$$ are likely to be defective in part $$Y$$. Calculate the probability that the assembled product will not be defective.

  • Question 5
    1 / -0

    The corner points of the feasible region determined by the system of linear constraints are $$(0, 10), (5, 5), (15, 15), (0, 20)$$. Let $$z=px+qy$$ where $$p, q > 0$$. Condition on p and q so that the maximum of z occurs at both the points $$(15, 15)$$ and $$(0, 20)$$ is __________.

  • Question 6
    1 / -0

    Corner points of the bounded feasible region for an LP problem are $$A(0,5) B(0,3) C(1,0) D(6,0)$$. Let $$z = -50x + 20y$$ be the objective function. Minimum value of z occurs at ______ center point.

  • Question 7
    1 / -0

    The corner points of the feasible region are $$A(0,0),B(16,0),C(8,16)$$ and $$D(0,24)$$. The minimum value of the objective function $$z=300x+190y$$ is _______

  • Question 8
    1 / -0

    The given table shows the number of cars manufactured in four different colours on a particular day. Study it carefully and answer the question.

     Colour   Number of cars manufactured
     Vento CretaWagonR 
     Red 65 88 93
     White 54 42 80
     Black 66 52 88
     Sliver37 49 74
    Which car was twice the number of silver Vento?

  • Question 9
    1 / -0

    A firm manufactures three products $$A,B$$ and $$C$$. Time to manufacture product $$A$$ is twice that for $$B$$ and thrice that for $$C$$ and if the entire labour is engaged in making product $$A,1600$$ units of this product can be produced.These products are to be produced in the ratio $$3:4:5.$$ There is demand for at least $$300,250$$ and $$200$$ units of products $$A,B$$ and $$C$$ and the profit earned per unit is Rs.$$90,$$ Rs$$40$$ and Rs.$$30$$ respectively.

    Raw
    material
    Requirement per unit product(Kg)
    A
    Requirement per unit product(Kg)
    B
    Requirement per unit product(Kg)
    C
    Total availability (kg)
    $$P$$$$6$$$$5$$$$2$$$$5,000$$
    $$Q$$$$4$$$$7$$$$3$$$$6,000$$
    Formulate the problem as a linear programming problem and find all the constraints for the above product mix problem.

  • Question 10
    1 / -0

    Equation of normal drawn to the graph of the function defined as $$f(x)=\dfrac{\sin x^2}{x}$$, $$x\neq 0$$ and $$f(0)=0$$ at the origin is?

Submit Test
Self Studies
User
Question Analysis
  • Answered - 0

  • Unanswered - 10

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
Submit Test
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now