Self Studies

Environmental Engineering Test 1

Result Self Studies

Environmental Engineering Test 1
  • Score

    -

    out of -
  • Rank

    -

    out of -
TIME Taken - -
Self Studies

SHARING IS CARING

If our Website helped you a little, then kindly spread our voice using Social Networks. Spread our word to your readers, friends, teachers, students & all those close ones who deserve to know what you know now.

Self Studies Self Studies
Weekly Quiz Competition
  • Question 1
    2 / -0.33
    In water softening processes, the purpose of re-carbonation after using lime-soda process is for
    Solution

    Complete removal of hardness cannot be accomplished by chemical precipitation. Precipitation of the supersaturated solution of CaCO3 will continue slowly, however, resulting in deposits in water lines and storage facility. It is, therefore, necessary to stabilize the water concerting supersaturated CaCO3 back to soluble form. This process is generally known as re-carbonation.

    The most common practice is

    \(\begin{array}{l} CaC{O_3} + C{O_2} + {H_2}O \to C{a^{2 + }} + 2\left( {HCO_3^ - } \right)\\ Mg{\left( {OH} \right)_2} + 2C{O_2} \to M{g^{2 + }} + 2\left( {HCO_3^ - } \right) \end{array}\)

  • Question 2
    2 / -0.33
    An aeration basin with a volume of 400 m3 contains mixed liquor with a suspended solids concentration of 1000 mg/l. The amount of mixed liquor suspended solids in the tank is
    Solution

    Concept:

    The total microbial mass in the aeration system (M) is computed by multiplying the average concentration of solids in the mixed liquor of the aeration tank, called Mixed Liquor Suspended Solids with the volume of the tank (V).

    ∴ M = MLSS × V

    Calculation:

    The concentration of mixed liquor suspended solids,

    MLSS = 1000 mg/l ⇒ \(\frac{{1000 \times {{10}^{ - 6}}}}{{{{10}^{ - 3}}}}\;kg/{m^3} = \;1\;kg/{m^3}\)

    For a volume of 400 m3,

    M = 1 × 400 = 400 kg

    ∴ The total concentration of mixed liquor suspended solids (M) would be 400 kg.
  • Question 3
    2 / -0.33
    When the friction factor is increased from 0.01 to 0.02, the self-cleansing velocity of the pipe _____
    Solution

    Concept:

    The self-cleansing velocity is the minimum velocity through which the sewage should flow through sewer such that there’s no silt deposition along its length.

    \({{\rm{v}}_{\rm{s}}} = \sqrt {\frac{{8 \times k \times g \times d \times \left( {G - 1} \right)}}{f}}\)

    where

    k = sediment coefficient

    f = frictional factor

    g = acceleration due to gravity

    G = specific gravity

    d = mean diameter of the silt

    Calculation:

    From the above formula, \({{\rm{v}}_{\rm{s}}} \propto \frac{1}{{\sqrt f }}\)

    \(\therefore \frac{{{{\rm{v}}_{{\rm{s}}1}}}}{{{v_{s2}}}} = \frac{{\sqrt {{f_2}} }}{{\sqrt {{f_{\;1}}} }} \Rightarrow {v_{s2}} = \frac{1}{{\sqrt 2 }} \times {v_{s1}}\)

    ∴ With an increase in friction factor from 0.01 to 0.02, the self-cleansing velocity of the pipe decreases by √2 times.
  • Question 4
    2 / -0.33
    The incorrect statement related to carbon/Nitrogen ratio is
    Solution

    Concept:

    Carbon-nitrogen ratio:

    • C/N of the input material is an important factor for the bacterial activity to continue, since the bacteria use nitrogen for building their cell structures and carbon for food.
    • The anaerobic bacteria, use up carbon about 30-50 times faster than they use up nitrogen. For proper growth of anaerobic digestion, C/N ratio of the digestive material should be between 30 to 50 for optimum digestion.
    • When there is too much of carbon, i.e. C/N ratio is higher than the optimum, then nitrogen will be used up and carbon left over, thereby leaving the digestion of organic matter incomplete.
    • When there is too much of nitrogen, i.e C/N ratio is lower than the optimum, then the carbon get exhausted and fermentation stop, leaving nitrogen in the digestor which combines with hydrogen to form ammonia (NH3). This can inhibit growth of bacteria mostly the methane formers.
    • The anaerobic digestion requires an optimum C/N ratio of 30-50.

  • Question 5
    2 / -0.33
    If the total hardness present in a water sample is 320 mg/L as CaCO3 and total alkalinity is 280 mg/L as CaCO3, the CH and NCH of the sample is (in mg/L as CaCO3)
    Solution

    Concept:

    Hardness: It is defined as the concentration of multivalent metallic cations in solution. Multivalent metallic ions most abundant in natural water are Calcium & Magnesium. Other ions that lead to hardness are Fe2+, Mn2+, Strontium (Sr2+) and Aluminium (Al3+). For all practical purposes, hardness may be represented by the sum of Ca2+ and Mg2+, ions as other cations are present in negligible amount.

    Hardness can be divided into two parts i.e. carbonate hardness and non-carbonate hardness.

    Case 1: If Total hardness is greater than Total alkalinity

    Carbonate hardness = Total alkalinity and Non-carbonate hardness = Total hardness - Carbonate Hardness

    Case 2: If Total hardness is less than Total alkalinity

    Carbonate hardness = Total alkalinity and Non-carbonate hardness = 0 (zero)

    Calculation:

    TH = 320 mg/L, Total alkalinity = 280 mg/L

    ∵ TH > TA

    ∴ Carbonate Hardness = Minimum of TH and TA = 280 mg/L

    ∴ Non Carbonate Hardness = Total hardness – CH = 320 – 280 = 40 mg/L

  • Question 6
    2 / -0.33

    A standard multiple-tube fermentation test was conducted on a sample of water. The analysis of the confirmed test are:

    Sample size (mL)

    No. of positive result out of five

    No. of negative results out of five

    10

    4

    1

    1

    3

    2

    0.1

    2

    3

    0.01

    0

    5

    MPN index for combinations of positive results when 5 tubes are used per dilutions (10 mL, 1 mL, 0.1 mL)

    Combination

    MPN index per 100 mL

    5 – 3 – 2

    33

    4 – 3 – 2

    26

    0 – 2 – 3

    22

    3 – 2 – 0

    7

    Using the MPN index table, the most probable number of the sample is

    Solution

    Concept:

    When more than three dilutions of samples are used (like 10 ml, 1 ml, 0.1 ml, 0.01 ml, 0.001 ml, 5-different dilutions), following procedure is adopted to obtain MPN from MPN chart:

    (a) Only three consecutive dilutions are used to determine MPN

    (b) If all dilutions tested yield positive result, select the three highest dilutions.

    (c) If one or more dilutions have all tubes positive, select the highest dilutions (i.e. smallest sample quantity like from 10 ml, 1 ml chose 0.1 ml) with positive result and next two higher dilutions.

    (d) When none of the dilution yield all tubes positive, select the three lowest dilutions for which middle dilution contains positive result.

    (e) If a positive result occurs in a higher unselected dilution, add the no. of positive tubes in the dilution to the result of the highest dilution of the three selected.

    Calculation:

    Choosing the three lowest dilution because none of the dilutions yield all positive results,

    MPN will be corresponding to 4 – 3 – 2 of 10 mL, 1 mL and 0.1 mL respectively.

    MPN = 26

  • Question 7
    2 / -0.33
    The aerobic method of mechanical composting practised in India is called:
    Solution

    There are mainly two methods (Indore and Bangalore method) adopted in India for decomposition of Solid wastes generated. The main difference between Indore Method and Bangalore Method for decomposition of MSW is given below:

    Indore Method

    Bangalore Method

    Decomposition of MSW by composting is done aerobically.

    Decomposition of MSW by composting is done an-aerobically.

    Decomposition takes 2-3 Months

    Decomposition takes 5-6 Months

    Mixing is ensure either Mechanically or manually

     No mixing is done.

  • Question 8
    2 / -0.33
    NOX presence in the atmosphere is detected by which of the following method?
    Solution

    Pollutants

    Method of Estimation

    COX

    NDIR Analyzer

    NOX

    Jacob & Oyster Method

    SOX

    West and Greek Method

    Suspended Particulate Matter

    High Volume Sampler Method

  • Question 9
    2 / -0.33
    Which of the following statement is not true regarding the usage of copperas as coagulant?
    Solution

    The most effective chemical to be used as coagulants are alum, ferrous sulphate, ferric chloride, ferric chloride, and ferric sulphate.

    a) Use of Alum (Al2 (SO4)3.18H2O) as coagulant:

    Alum or filter alum has proved to be a very effective coagulant, and it is now extensively used throughout the world. It is quite cheap, forms an excellent stable floc, and does not require any skilled supervision for handling.

    Al2(SO4)3.18H2O + 3Ca(HCO3)2 → 3CaSO4 + 2Al(OH)3 + 6 CO2

    The only drawback in the use of alum is that the effective pH range for its use is small, i.e. 6.5 to 8.3, and in many cases it requires the addition of external alkali salts, thereby rendering it costlier.

    b) Use of Copperas (FeSO4.7H2O) as coagulant:

    Copperas (FeSO4.7H2O) is extensively used as a coagulant for raw waters that are not coloured. It is generally cheaper than alum and functions effectively in the pH range of 8.5 and above.

    \({\bf{FeS}}{{\bf{O}}_4}.7{{\bf{H}}_2}{\bf{O}} + {\bf{Ca}}{\left( {{\bf{OH}}} \right)_2} \to {\bf{CaS}}{{\bf{O}}_4} + {\bf{Fe}}{\left( {{\bf{OH}}} \right)_2} + 7{{\bf{H}}_2}{\bf{O}}\)

    it is not used for coloured raw waters. The quantity of copperas required is almost the same as that of alum.

    c) Use of Chlorinated copperas as coagulant:

    The resultant combination of ferric sulphate and ferric chloride is known as chlorinated copperas, and is a valuable coagulant of removing colours, especially where the raw water has a low pH value.

    6(FeSO4.7H2O) + 3Cl2 → 2Fe2(SO4)3 + 2FeCl3 + 42H2O

    Ferric sulphate is quite effective in the pH range of 4 to 7 and above 9, whereas Ferric chloride is quite effective in the pH range of 3.5 to 6.5 and above 8.5. The combination has, therefore, proved to be a very effective coagulant for treating low pH waters.

    d) Use of sodium aluminate (Na2 Al2 O4) as coagulant:

    \({\rm{N}}{{\rm{a}}_2}{\rm{A}}{{\rm{l}}_2}{{\rm{O}}_4} + {\rm{Ca}}{\left( {{\rm{HC}}{{\rm{O}}_3}} \right)_2} \to {\rm{CaA}}{{\rm{l}}_2}{{\rm{O}}_4} + {\rm{N}}{{\rm{a}}_2}{\rm{C}}{{\rm{O}}_3} + {\rm{C}}{{\rm{O}}_2} \uparrow + {{\rm{H}}_2}{\rm{O}}\)

    This coagulant is about 1½ times costlier than alum, and is, therefore, generally avoided for treating ordinary public supplies, but, however, it is very useful for treating waters which do not have the natural desired alkalinity, and thus cannot be treated with pure alum.

    This coagulant is, therefore, widely used for treating boiler feed waters, which permit very low values of hardness.
  • Question 10
    2 / -0.33
    A raw water sample collected from a lake was subjected to tests for estimation of solids. A one liter of raw water when passed through filter paper, the moist weight of filter paper is 225 gm which after oven drying was reduced to 200 grams. The filtered water is then over dried for 5 hours resulting in 150 grams of solids, the remaining solid when subjected to the heating in the metal furnace was reduced to 100 grams. A separate test on the raw material conducted through gravimetry resulted in 300 milligrams of solids. The non-volatile and volatile dissolved solid (in mg/liter), in the water sample respectively are ____. 
    Solution

    Concept:

    Estimation of solids:

    (1) Total solid (Suspended + Dissolved)

    a) Determined by gravimetry test

    b) Raw water when heated at 104 - 105°C for 4-5 hours resulted in total solid.

    (2) Suspended solid

    Raw water when passed through Whattman filter paper no. 9, the filter paper collects suspended solids which when dried under hot air oven gives total suspended solid.

    (3) Dissolved solid

    The filtered water when heated at 104° - 105°C for 4 to 5 hours gives dissolved solids, which when subjected to mettle furnace (700°C - 1000°C for 4 to 5 hours) results in nonvolatile solids and hence the difference obtained is volatile solid.

    Calculation:

    From above:

    Total dissolved solids: 150 milligrams

    Nonvolatile solids = 100 milligrams

    Volatile solids = 50 milligrams

  • Question 11
    2 / -0.33
    The present population of a sector in Noida is 200,000 with an average water consumption of 50000 m3/d. The design capacity of water treatment plant is 75000 m3/day. Due to expansion of the sector it is expected that the population will increase to 325,000 during the next 10 years. The number of years from now when the plant will reach its design capacity assuming an arithmetic rate of population growth, will be
    Solution

    Population after n years

    Pn  = P0 + n

    \(\begin{array}{l} \Rightarrow \;\bar x = \frac{{{p_n} - {p_0}}}{n}\\\therefore \bar x = \frac{{325\;000 - 200\;000}}{{10}}\end{array}\)

    \(\bar x = 12500\)

    Discharge required to reach design capacity

    = 75000 – 50000

    = 25000 m3/d

    Present average water consumption per head per day

    \(= \frac{{50000}}{{200000}} = \frac{1}{4}{m^3} = 0.25{m^3}\)

    Increase in water consumption each year

    = 0.25 × 12500

    = 3125 m3/ day.

    Number of years required to reach design capacity \(= \frac{{25000}}{{3125}}\;years\)

    = 8 years
  • Question 12
    2 / -0.33
    A branch sewer to be designed at the half flow condition for a town for the population of 10000 has an average daily water supply at the rate of 200 lpcd. 80 percent of the water supplied goes to drain. The sewer is designed to carry three times of average discharge. If the branch sewer is laid at the slope of 0.005 and the manning’s roughness coefficient for the sewer material is 0.009, then the suitable diameter of the pipe is _________
    Solution

    Concept:

    Sewers are never designed for the full flow condition because the fluctuation in discharge can be higher and in wastewater some gases are also released, and these gases occupies the empty space.

    These are always designed for the maximum hourly discharge and for branch sewer maximum hourly discharge is three times the average daily discharge.

    For half flow condition, discharge is also half of full flow discharge. Since flow in sewers is open channel flow so manning equation is valid here,

    Discharge in open channel by manning’s equation:

    \({\rm{Q}} = \frac{1}{{\rm{n}}} \times {\rm{A}} \times {{\rm{R}}^{\frac{2}{3}}} \times {{\rm{S}}^{\frac{1}{2}}}\)

    Where,

    Q = discharge, n = manning’s roughness coefficient, A = area of flow, R = hydraulic radius, and S = slope of channel

    Calculation:

    Population = 10000, Water supply rate = 200 lpcd, and Wastewater generation rate = 80%

    Design discharge= 3 × 10000 × 200 × 0.80 = 3 × 1.6 × 106 L/day = \(\frac{{3 \times 1.6 \times {{10}^6} \times {{10}^{ - 3}}}}{{24 \times 3600}} = 0.05555{\rm{\;}}{{\rm{m}}^3}/{\rm{s}}\)

    Discharge in half flow sewer is half of full flow sewer:

    ∴ Discharge in full flow sewer = 2 × 0.0555 = 0.1111 m3/s.

    According manning’s equation:

    \({\rm{Discharge\;}}\left( {\rm{Q}} \right) = \frac{1}{{\rm{n}}} \times {\rm{A}} \times {{\rm{R}}^{\frac{2}{3}}} \times {{\rm{S}}^{\frac{1}{2}}}\)

    For circular section,

    \(\therefore {\rm{Q}} = \frac{1}{{\rm{n}}} \times \frac{{{\rm{\pi }}{{\rm{D}}^2}}}{4} \times {\left( {\frac{{\frac{{{\rm{\pi }}{{\rm{D}}^2}}}{4}}}{{{\rm{\pi D}}}}} \right)^{\frac{2}{3}}} \times {{\rm{S}}^{\frac{1}{2}}} = \frac{1}{{\rm{n}}} \times \frac{{{\rm{\pi }}{{\rm{D}}^2}}}{4} \times {\left( {\frac{{\rm{D}}}{4}} \right)^{\frac{2}{3}}} \times {{\rm{S}}^{\frac{1}{2}}} = \frac{{{\rm{\pi }} \times {{\rm{D}}^{8/3}} \times {{\rm{S}}^{1/2}}}}{{10.08{\rm{\;n}}}}\)

    \(\therefore 0.111= \frac{{{\rm{\pi }} \times {{\rm{D}}^{8/3}} \times {{0.005}^{1/2}}}}{{10.08 \times 0.009}} \Rightarrow {\rm{D}} = 0.31{\rm{\;m}}\)
  • Question 13
    2 / -0.33
    The amount of bleaching powder having 25% chlorine required to chlorinate water supply for 50000 people at the rate of 50 lpcd having a chlorine demand of 2 mg/ℓ is
    Solution

    Concept:

    Chlorine Demand: The difference between applied chlorine and residual chlorine at or beyond break-point is called chlorine demand of water.

    Calculation:

    Total water disinfected = 50000 × 50 = 2.5 × 106 L/Day

    Chlorine Demand = 2 mg/L

    Total amount of chlorine required = (2.5 × 106) × 2 × 10-6 kg/day= 5 kg/day

    Since bleaching powder contains only 25% chlorine

    Total Bleaching powder required \(= \frac{5}{{0.25}} = 20\;kg\)

    Important Point:

    The dose of chlorine should be such that 0.2 mg/L is left in the water after a contact period of 30 min  to prevent against future contamination.

  • Question 14
    2 / -0.33
    A town with a population of 60000 produces a solid waste at 3 kg/capita/day. A survey on this waste reveals that the 50 percent of the waste constitutes of food waste having a specific weight of 300 kg/m3, while 30 percent is dirt and ash with a specific density of 500 kg/m3 and the remaining 20 percent of waste has weighted average specific density of 100 kg/m3. If this solid waste is to be dumped directly on the landfill of 5 meters depth. Calculate the area of the landfill (in hectares) required annually to accommodate such waste disposal.
    Solution

    The survey conducted on the waste is as follows:

    Component

    Percent

    Density (kg/m3)

    Food waste

    50

    300

    Dirt & ash

    30

    500

    Miscellaneous

    20

    100


    The average density of the solid waste (ρsw) is given by:

    \(\frac{{100}}{{{{\rm{\rho }}_{{\rm{sw}}}}}} = \frac{{50}}{{300}} + \frac{{30}}{{500}} + \frac{{20}}{{100}}\)

    ρsw = 234.375 kg/m3

    Solid waste produced annually = 6000 × 3 × 365 = 65700000 kg

    Volume of landfill = \(\frac{{65700000{\rm{\;}}}}{{234.375}} = 280320{\rm{\;}}{{\rm{m}}^3}\) 

    Area of landfill \(= \frac{{280320}}{5} \times {10^{ - 4}} = 5.60{\rm{\;hectares\;}}\)

  • Question 15
    2 / -0.33

    An anaerobic digester is designed to remove 85% of BOD of industrial organic waste with an ultimate BOD of 2000 mg/L. If the sludge age (θc) is 10 days, estimate the amount of sludge (kg/day) to be wasted on a daily basis_____.

    Assume the following data

    Flow (Q) of 0.1 MLD,

    Y = 0.1 kg/kg,

    kd = 0.01 per day and

    k = 0.23 per day
    Solution

    Given:

    Ultimate BOD(L0) = 2000 mg/L

    BOD5 = L0 (1 – e-kt)

    BOD5 = 2000(1 – e-0.23×5)

    BOD5 = 1366.73 mg/L

    ∴ So = BOD5 = 1366.73 mg/L

    \({S_o} = \frac{{1366.73 \times {{10}^{ - 6}}}}{{{{10}^3}}} = 1.367\;kg/{m^3}\)

    Also, S = 15% of So

    Therefore, \(S = \frac{{15}}{{100}} \times 1.367\)

    S = 0.205 kg/m3

    Flow, Q = 0.1 × 106 × 10-3 m3/day

    Q = 100 m3/day

    Therefore, sludge age can be written as

    \(\frac{1}{{{\theta _c}}} = \frac{{\left( {S - {S_o}} \right)YQ}}{{VX}} - {k_d}\)

    \(\frac{1}{{10}} = \frac{{\left( {1.367 - 0.205} \right) \times 0.1 \times 100}}{{VX}} - 0.01\)

    \(\Rightarrow VX = \frac{{1.162 \times 10}}{{0.09}}\)

    ⇒ VX = 105.63 kg

    Hence, sludge wasted \(= {Q_W}{X_u} = \frac{{VX}}{{{\theta _C}}}\)

    \(\Rightarrow {Q_w}{X_u} = \frac{{105.63\;}}{{10}}\) kg/day

    ⇒ QwXu = 10.56 kg/day

    Hence, the amount of sludge wasted on daily basis is 10.56 kg.
  • Question 16
    2 / -0.33
    A town having a population of 30000 persons is producing sewage at the rate of 120 lpcd with initial BOD of waste being 250 mg/l. If 30% of the B.O.D is removed in the primary clarifier itself, then determine the minimum required volume (in m3) of high rating trickling filter for achieving desired effluent BOD of 30 mg/l. (Assume recirculation ratio of 1.5).
    Solution

    Concept:

    the efficiency of trickling filter is given by:

    \({\rm{\eta }} = \frac{{100}}{{1 + 0.44\sqrt {\frac{{\rm{W}}}{{{\rm{V}} \times {\rm{F}}}}} }}\)

    Where,

    W = BOD of wastewater entering in filter unit (kg/day)

    V = Volume of filter (in m3)

    F = Recirculation factor \(= \frac{{1 + R}}{{{{\left( {1 + 0.1R} \right)}^2}}}\)

    R = Recirculation ratio

    Calculation:

    Total sewage discharge \(= \frac{{30000 \times 120}}{{{{10}^6}}} = 3.6{\rm{MLD}}\)

    BOD of wastewater initially = 250 mg/l

    BOD of water after primary clarifier = 250 × 0.7 = 175 mg/l

    BOD of desired effluent = 30 mg/l

    \({\rm{Efficiency\;}}\left( {\rm{\eta }} \right) = \frac{{175 - 30}}{{175}} \times 100 = 82.86{\rm{\% }}\)

    Now,

    W = 3.6 × 175 = 630 kg/day

    \({\rm{F}} = \frac{{1 + 1.5}}{{{{\left( {1 + 0.1 \times 1.5} \right)}^2}}} = 1.89\)

    \(\therefore 82.86 = \frac{{100}}{{1 + 0.44\sqrt {\frac{{650}}{{{\rm{V}} \times 1.89}}} }}\)

    ∴ V = 1507.89 m3
  • Question 17
    2 / -0.33
    Three sources generate noise levels of 60 dB, 80 dB and 100 dB respectively. The average sound pressure level is (in dB upto 2 decimal places) _______
    Solution

    Concept:

    The average value of the various recorded sound pressure levels (Lp) over a given period cannot be computed by simple averaging due to log scale involved in their values.

    Average pressure level

    \({\bar L_p} = 20\log \frac{1}{N}\mathop \sum \limits_{n = 1}^{n = N} {\left( {10} \right)^{{L_{n/20}}}}\)

    Where,

    p = Average sound pressure level in dB

    N = Number of measurement readings

    Ln = nth sound pressure level in dB

    n = 1, 2, 3, …. N

    Calculation:

    L1 = 60 dB, L2 = 80 dB, L3 = 100 dB, N = 3

    Average sound pressure level (Lavg)

    \(= 20{\log _{10}}\frac{1}{N}\mathop \sum \limits_{n = 1}^{n = N} {\left( {10} \right)^{{L_{n/20}}}}\)

    \( = 20{\log _{10}} \times \frac{1}{3}\left[ {{{10}^{\frac{{60}}{{20}}}} + {{10}^{\frac{{80}}{{20}}}} + {{10}^{\frac{{100}}{{20}}}}} \right]\) = 91.36 dB

  • Question 18
    2 / -0.33
    A city having a population of 100000 with an average demand of 160 lpcd to be provided with a rapid sand filter. Each backwashing period is of 30 mins and 5% of filtered water is used for backwashing. If the rate of filtration is 4000 L/hr/m2 and area of 1 filter bed  is 50 m2 the number of filters required allowing 1 as a stand by is
    Solution

    Concept:

    Rapid sand filters are designed for the maximum daily demand and backwash water required.

    Maximum Daily Demand = 1.8 × Average daily demand

    Calculation:

    Qavg = 100000 × 160 = 16 × 106 litre per day

    Assuming 5% as backwash and 30 minutes of back-washing period,

    \({Q_{design}}\;\left( {l/d} \right) = \left[ {\frac{{1.8 \times {Q_{avg}} + 0.05 \times {Q_{avg}}}}{{23.5}}} \right] \times 24\) \(= \left[ {\frac{{1.8 \times 16 \times {{10}^6} + 0.05 \times 16 \times {{10}^6}}}{{23.5}}} \right] \times 24\) = 30.23 × 106 ℓ/d

    Rate of filtration = 4000 ℓ/hr/m2  = 4000 × 24 = 96000 ℓ/day/m2

    Total plan area of filters required \(= \frac{{{Q_{design}}}}{{Rate\;of\;filtration}} = \frac{{30.23 \times {{10}^6}}}{{96000}} = 314.90\;{m^2}\)

    Number of filters required \(= \frac{{Total\;plan\;area}}{{Plan\;area\;of\;1\;filter}} = \frac{{314.90}}{{50}} = 6.3\)

    Thus adopting 7 filters and 1 on stand by, total number of filters required = 8

    Important Point:

    The number of Rapid sand filters required if the rate of filtration is not known is given as

    \(n = 1.22\;\sqrt Q\),  Where, Q = Design Discharge in MLD

  • Question 19
    2 / -0.33
    An ideal horizontal flow setting tank having a plan area of 800 m2 is used for settling of solids in water flowing at a rate of 32000 m3/day. Assuming stokes law to be valid, the percentage removal of spherical sand particles of 0.018 mm diameter with a specific gravity 2.7 is (Take νwater = 1.01 × 10-2 cm2/s)
    Solution

    Concept:

    Surface overflow rate: It can be thought of as the settling velocity of that particle if introduced at the topmost point at the inlet of the tank gets settled at the bottom-most point just before the outlet of the tank.

    Particles having sizes greater than the particles for which setting velocity is equal to overflow rate gets 100% removed.

    Particles having settling velocity less than overflow rate will not get 100% removed.

    The percentage removal of particles having settling velocity Vs' is given as \(=\frac{{{V}_{s}}'}{{{V}_{s}}}\times 100\)

    Where, VS’ = Settling velocity of smaller size particles.

    Settling velocity is calculated by Stoke’s law for discrete particle settling. It is given as-

    \(V_{s}^{'}=\frac{\left( {{G}_{s}}-1 \right) {g{d}^{2}}}{18~\nu }\)

    Where Gs = Specific gravity of particles.

    d = Particle size

    ν = Kinematic Viscosity of fluid in which particle is settling.

    Calculation:

    Plan area = 800 m2, Q = 32000 m3/day

    Overflow rate \(({V_s}) = \frac{Q}{{Plan\;area}} = \frac{{32000}}{{800}}\) = 40 m/day = 0.463 mm/s

    For sand particles:

    Gs = 2.70, dp = 0.018 mm, νwater = 1.01 × 10-2 cm2/s

    As per stoke’s law, settling velocity of the sand particles,

    \(V_s' = \frac{{\left( {{G_s} - 1} \right) \times g \times d_p^2}}{{18\;\nu }} = \frac{{\left( {2.7 - 1} \right) \times 9.81 \times {{\left( {0.018 \times {{10}^{ - 3}}} \right)}^2}}}{{18 \times \left( {1.01 \times {{10}^{ - 2}} \times {{10}^{ - 4}}} \right)}}\) = 2.97 × 10-4 m/s = 0.297 mm/sec

    Percentage removal \(= \frac{{{V_s}'}}{{{V_s}}} \times 100 = \frac{{0.297}}{{0.463}} \times 100\) = 64.15%

    Important point:

    • Discrete Particle settling is assumed in stokes law and applicable for laminar flow for Reynolds number < 1.
    • The efficiency of the sedimentation tank is independent of the depth of the tank and depends only on the plan area of the tank.
  • Question 20
    2 / -0.33
    An electrostatic precipitator with collecting area “A” m2 has existing efficiency of 92 % is installed at a particular place. If it is desired to increase its existing efficiency to 98%, the collector area must be increased ‘x’ times that of the existing collecting area. The suitable value of x, rounded up to two decimal places is _______
    Solution

    Concept:

    Fractional collection efficiency of Electrostatic precipitator is given by:

    \({\rm{\eta }} = 1 - {{\rm{e}}^{ - \frac{{{\rm{WA}}}}{{\rm{Q}}}}}\)

    Where

    W = terminal drift velocity (m/s), A = Total collection area (m2), and Q = Volumetric air flow rate (m3/s)

    Calculation:

    Let,

    η1 = Exiting fractional efficiency of electrostatic precipitator, η2 = New fractional efficiency of electrostatic precipitator, A1 = Existing collection area, and A2 = New collection area

    \({{\rm{\eta }}_1} = 1 - {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_1}}}{{\rm{Q}}}} \right)}}\)

    \( ⇒ 0.92 = 1 - {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_1}}}{{\rm{Q}}}} \right)}}\\ ⇒ 0.08 = {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_1}}}{{\rm{Q}}}} \right)}}\)

    ⇒ 2.5257 = WA1/Q

    \({{\rm{\eta }}_2} = 1 - {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_2}}}{{\rm{Q}}}} \right)}}\)

    \(⇒ 0.98 = 1 - {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_2}}}{{\rm{Q}}}} \right)}}\\⇒ 0.028 = {{\rm{e}}^{\left( { - \frac{{{\rm{W}}{{\rm{A}}_2}}}{{\rm{Q}}}} \right)}}\)

    ⇒ 3.5756 = WA2/Q

    Solving both equations,

    A2 = 1.548 A1

    So, collecting area must be 1.548 times of existing area

Self Studies
User
Question Analysis
  • Correct -

  • Wrong -

  • Skipped -

My Perfomance
  • Score

    -

    out of -
  • Rank

    -

    out of -
Re-Attempt Weekly Quiz Competition
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now