  • Question 1
    1 / -0

    In a forecasting analysis, it is required that higher weightage be given to recent demand information, the smoothening constant for this should be_________

  • Question 2
    1 / -0

    Calculate the difference between 4-week and three-week moving average forecast for 2020

    Year

    2015

    2016

    2017

    2018

    2019

    Demand

    55

    60

    58

    65

    72

  • Question 3
    1 / -0

    If the previous year forecast was 110 units and actual demand was 115 units, the forecast for current year using exponential smoothening method with smoothening constant equal to 0.3 is _____

  • Question 4
    1 / -0

    Find the ratio of mean forecast error to mean absolute deviation. For the given data _____.

    Year

    Demand

    Forecast

    2013

    250

    235

    2014

    260

    265

    2015

    265

    272

    2016

    270

    252

  • Question 5
    1 / -0

    In a forecasting model, the linear regression technique was used for a time series forecasting method which gave the equation: F = 7 + 3t, where F is the forecast for the period. The demand for the five periods of time were 11, 14, 16, 20, 25. The sum of the absolute deviations for the above data is:

  • Question 6
    1 / -0

    For a regression model

    ∑ x = 36, ∑ y = 5432, ∑ x2 = 204, ∑ xy = 26108.8 and n = 8

    The forecast regression equation slope and constant for the data, respectively, are___

  • Question 7
    1 / -0

    Five architectural rendering jobs are waiting to be assigned at OM architects. Their work (processing) times & due dates are given in following table.

    Job

    Job work

    time (days)

    Job due

    date (days)

    A

    B

    C

    D

    E

    5

    2

    7

    3

    8

    8

    6

    17

    14

    21

     

    The jobs are sequenced according to SPT rule, then find ratio between average job completion time & total job lateness time?

  • Question 8
    1 / -0

    Two operations facing, and threading are to be performed on 6 jobs. The time required for performing the jobs are shown below.

    Job

    Time for facing in minutes

    Time for threading in minutes

    1

    3

    8

    2

    12

    10

    3

    5

    9

    4

    2

    6

    5

    9

    3

    6

    11

    1

     

    The total idle time for the operations is________minutes

Submit Test
Self Studies
User
Question Analysis
  • Answered - 0

  • Unanswered - 8

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
Submit Test
Selfstudy
Selfstudy
Self Studies Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Self Studies
Click on Allow to receive notifications
Allow Notification
Self Studies
Self Studies Self Studies
To enable notifications follow this 2 steps:
  • First Click on Secure Icon Self Studies
  • Second click on the toggle icon
Allow Notification
Get latest Exam Updates & FREE Study Material Alerts!
Self Studies ×
Open Now